2 SBTL5000 series installation guide
2
Installation
1.
Drill holes based on the drawing of mount holes position, as shown in Figure 2-1.
Then set the expansion screw into holes.
Figure 2-1
2.
Pre-fixed the device by these expansion screws. Then connect the wires between
master and slave devices. As shown in below:
Figure 2-2 (5-core: signal, 2-core: 24V power)
3.
Test with temporary cable, ensure that ground wire of AC power was connected to
cabinet.
4.
Turn on the air switch to test whether the device is working properly, wait for 10
seconds for the gate to complete self-test program. At the same time check
whether or not the indicator light working properly. If everything is normal, you