807062 v1.00 03.21 EB HB Install Instructions
Step 6 – Commissioning
Check water connections
Turn ON the mains water supply. Water will flow into the
Hydroboil. Check connections and repair any leaks.
Depress the tap lever into the locked open position. Allow the tank to
fill until water flows from the tap outlet.
Once water is available from the tap, close the tap to stop water flow.
Turn ON electrical power
Boiling Calibration will commence. The tank will fill and heat. Allow 15-30 minutes for the water
to reach boiling set temperature.
6.2
6.3
Check earthing
Earthing continuity must be tested by a qualified technician
using a resistance meter of minimum accuracy of 5% full scale
deflection.
• Ensure electrical power is OFF.
• Verify meter ohms range, connect leads together, reading
should be 0 ohms.
• Hold one test lead to the earth of the power lead.
• Hold the other test lead on a cover fixing screw, then the
tap.
• Verify that in every instance the electrical resistance does
not exceed 1 ohm.
Warning: This appliance must be earthed
Do not turn ON electrical power until instructed. Water must be
available from the tap outlet to prevent damage. Water dispensed
during commissioning may be boiling.
!
6.1
< 1.0 Ω