Working method

The ZIEGRA chip-ice machine is delivered ready for operation and has only to be connected to power and water supply.

No operating personnel is required.
The machine works fully automatically.

Water flows by gravity from the water chamber in the ice-
machine into the freezing cylinder. An evaporating coil

(e.g. R404) surrounds the cylinder, freezing the water inside
at an evaporation temperature of -20° C up to - 30° C.

An auger continuously scrapes thin layers of ice from the
inner cylinder wall and conveys it upwards. There the ice
is compacted, frozen further and subsequently broken off.

By this procedure the refrigeration energy can freeze the followig water without loss.
If the ice layer would become 1 or 2 mm thick, an unnecessary amount of energy would have to be used for freezing
due to the high insulating capacity of ice.

 

The

 ideal ice thickness of 6 - 9 mm

 at low energy consumption can be achieved thanks to the idea of subsequently 

compacting the ice.

The ice being frozen on the inner wall of the cylinder, the refrigeration system of ZIEGRA Chip Ice Machines 
is completely sealed. The rotating auger does not form part of the refrigeration circuit.

Therefore leakages in the refrigeration system caused by rotating parts cannot occur.

The ideal ice temperature is  -0,5° C

ZIEGRA Chip-ice has the ideal temperature of - 0,5° C .

It is irregular and crystalline in structure and always stays loose.
In contrast with other types of ice it can be stored without being sub-cooled and never freezes up.

ZIEGRA-Cip-Ice

 is frozen within the patented freezing cylinder at an evaporation temperature of -20° C up to -30° C.

Due to the special procedure maximum refrigeration capacity is obtained at a very low energy consumption.

Cooling energy:

The uninterupted line shows the accumulated energy per kg of ice
(refrigeration energy). 
Only when ice having a temperature of 0° C
melts to water of 0° C, the considerable  

Refrigeration Capacity  of                   

80 Kcal / kg

is released (vertical line)

The cooling capacity of water per °C is 
(left line)

  1 Kcal / kg,

Ice tempeartures below 0° C give only

0,5 Kcal / kg.

Energy consumption:

The broken line shows the minimum electric energy consumption
necessary for every ice production.
For an ice temperature of 0° C energy input and the 
refrigeration capacity produced are closely correlated.
Only when ice is unnecessarily cooled to temperatures below 0° C,
the energy required rises disproportionately.

1

Содержание UBE 1.500

Страница 1: ...e quality Miscellaneous 7 Cleaning of freezing unit 8 Wiring diagram attached Cooling circuit General installation advice Assembly Instruction Freezing Unit Spare parts list Subject to technical modif...

Страница 2: ...tating auger does not form part of the refrigeration circuit Therefore leakages in the refrigeration system caused by rotating parts cannot occur The ideal ice temperature is 0 5 C ZIEGRA Chip ice has...

Страница 3: ...the machine Tighten all electrical connections in the control and at water temperatures above 15 C resp 25 C panel as they may have loosened during the production capacity may decrease transport Cran...

Страница 4: ...s full This light barrier has been chosen by us for these 10 Phase sequence Relay particular conditions Please contact us The phase sequence relay switches off the machine if the phases are not connec...

Страница 5: ...if necessary V belts check replace if necessary A loose V belt does not transfers the load correctly on the auger This will overload the freezing unit Ice hose and water retainer calcified clean or re...

Страница 6: ...eck connection and fuses Fuses blow up Check Intermittent contact Check electrical connections also in control panel Water pressurestat or readjust or replace Water level control defective readjust or...

Страница 7: ...cooled machine insufficient water pressure increase water pressure to min 2 bar condenser soiled clean condenser with bottle brush hot water and antilime agent clean water filter water or condensing p...

Страница 8: ...ust evaporation temperature as indicated Check thermal feeler pipe and contact at evaporator outlet insufficient amount of refrigerant remove leak evacuate circuit refill bubbles in sight glass with i...

Страница 9: ...unit into a container o Connect a hose of appr 80 cm with funnel at the water inlet of the freezing unit o Mix cleaning agent with hot water For each freezing unit 1 2 bottle agent in 1 litre water o...