K207A Swing Gate Opener User’s Manual
can be welded on the gate section with the lock so that when it closes, it will trap the gate section
without the lock between itself and the center stop block, thus locking both gate sections.
Mechanical Maintenance
z
Check the screw lubricant and add #1 grease regularly to both gate actuators.
z
Regularly verify that the gate swings freely and add grease regularly.
z
Keep opener clean at all times.
Electrical and Control Box Installation
1. Installation
(1) Install the cable
z
In order to protect the wires, between the gate opener and the control box, armored cable,
galvanized cable or PVC pipe must be set into the concrete when it is poured. Wires within the
cable shall be located or protected so that no damage can result from contact with any rough or
sharp part. The diameter of the cable should be more than 20mm, the wire size inside the cable
should be more than 1.0mm
2
.
(2) Install the control box
z
The control box circuit should be equipped with single-phase breaker (10A).
z
Make sure that power is OFF before making any electrical connections.
z
Open the cover of the control box, remove the control board, and fix the control box on the wall.
See Fig. 12
z
Perform the wiring and replace the cover. (See table 1 and Fig.14)
Note:
(1) we regard the gate with the electrical lock as No.1 gate, the other gate as No.2 gate. (2) If
you want to use auto-close function, the gate opener must be equipped with the infrared device.
Fig. 12 mounting size