STANDARD OPERATING PROCEDURE 
String Inverter Installation – Zeverlution Series 

 

Version 1.2 Effective date 02/08/2017

 

 

Page 4 of 15 

5.1.4

 

Maximum String Voltage 

The maximum length of a single string is dictated by the string voltage, taking temperature 
coefficients and the local ambient temperatures into account. For all solarcity installation zones, 
the maximum number of panels in a single string of 60-cell modules with a rated output at STC of 
less than or equal to 300 Watts, is ten (10). The string length is also limited by the DC isolator’s 
rating. 

 

String Inverter Installation 

The following section describes  the physical installation of the string inverter for solarZero  and 
solarClassic systems. The range of string inverters is currently limited to two models, a 2kW and a 
4kW unit. 

5.2.1

 

Zeversolar Zeverlution 2000s 

This inverter is used for systems with a peak output between 1.5kWp and 3kWp (6 to 10 modules), 
where the peak performance rating per panel at STC does not exceed 295Wp. 

 

For further details please refer to th

Zeverlution 2000s datasheet

. 

 

DC Input

 

The inverter is equipped with a single MPPT input. The single string is connected using 

SUNCLIX 

connectors 

of which one pair is supplied with the inverter.  

Model 

Zeverlution 2000s 

Convertible power 

2350W 

Max input voltage 

500V 

MPP voltage range 

70V - 450V 

Min DC start voltage 

80V 

Max DC input current 

11A 

 

AC Output 

The inverter has an AC screw terminal block for connecting the AC cabling.  

Model 

Zeverlution 2000s 

Rated active power 

2000W 

Max apparent power 

2200VA 

Rated grid voltage 

230V 

Max AC output current 

10A 

Min MCB rating 

16A (type C) 

 

5.2.2

 

Zeversolar Zeverlution 4000 

The Zeverlution 4000 inverter is used for systems with a peak output between 3.4kWp and 6kWp.  

 

For further details please refer to th

Zeverlution 4000 datasheet.

 

 

DC Input 

The inverter has 2 individual MPPT inputs and comes with 2 pairs of 

SUNCLIX 

connectors.  

Содержание Zeverlution 2000S

Страница 1: ...2 BEHAVIOURAL 2 SAFETY 2 INSTALLATION PROCEDURE 3 String Design Guidelines 3 5 1 1 String Layout Without Optimisers 3 5 1 2 String Layout with Optimisers 3 5 1 3 Shading 3 5 1 4 Maximum String Voltage...

Страница 2: ...d electrical part of the inverter installation instruction The focus of this SOP lies on the physical installation of Zeverlution 2000s and Zeverlution 4000 inverters and any associated switch gear DC...

Страница 3: ...4000 inverters and for arrays with or without optimisers the minimum and maximum strings lengths are as follows minimum number of modules per string is 3 maximum number of modules per string is 10 5 1...

Страница 4: ...systems with a peak output between 1 5kWp and 3kWp 6 to 10 modules where the peak performance rating per panel at STC does not exceed 295Wp For further details please refer to the Zeverlution 2000s da...

Страница 5: ...et which is used to fix the units to a suitable wall Please refer to the solarcity wall cladding guide for suitable wall claddings to mount the inverter on 1 Use the wall bracket as a drilling templat...

Страница 6: ...ble The inverter must not be installed in a location where it is exposed to direct sunlight Wiring 5 3 1 DC Wiring All wiring must be installed and sized in accordance with the relevant requirements o...

Страница 7: ...ted as per AS5033 The table below shows the maximum cable length one way between array and inverter with JA 290W panels allowing for a 2 voltage drop Panels per string 3 4 5 6 7 8 9 10 Max cable lengt...

Страница 8: ...to maintain the correct polarity the connectors are also marked with and symbols The steps below explain how to assemble SUNCLIX connectors Ensure that the array cable is de energized before installin...

Страница 9: ...lled on an appropriate roof penetration kit must be used Roof penetrations must always be located under the solar panels where an attic space is accessible for the cable run Where cable s pass through...

Страница 10: ...mm which is usually too short for leapfrog wiring Please use standard daisy chain wiring for all optimised array sections 5 3 3 AC Wiring The inverter is connected to the switchboard using double insu...

Страница 11: ...S 5033 2014 and follow the instructions outlined in the standard Attached to this document you ll find a commissioning sheet which you may use to record the test results A completed and signed copy of...

Страница 12: ...To confirm wait for approximately 10 seconds until the inverter automatically returns to the initial display showing the error code Connecting the inverter to the Internet The inverter needs to be co...

Страница 13: ...before setting up the WIFI connection 2 With the inverter powered up use a smartphone or laptop to search for the inverter s wireless access point This will display as ZEVERSOLAR XXXX Connect to this...

Страница 14: ...omer s wireless network 6 After approximately one minute the inverter should connect to the customers wifi network and the status indicator on the wireless page will show a green tick 7 Take a photo o...

Страница 15: ...rnet cable through the comms gland on the bottom of the inverter ensuring that the cable entry is sealed from dust and moisture 3 The inverter automatically obtains an IP address from the router via D...

Страница 16: ...rod MEN link removed Earth continuity 2 Main earth conductor to array frame Polarity check and PV open circuit voltage Polarity Voltage V String 1 String 2 if applicable PV array at switch disconnect...