2. Use the Zep Tool to rotate the Leveling Foot 90°
clockwise
until the base of the foot is parallel with
the roof surface (Figure 5.7C). With the fastener appropriate to mounting method being utilized,
secure the Leveling Foot to the mounting surface or attachment hardware.
NOTE:
It is important to NOT over or under-rotate the Leveling Foot since the drop-in
action on the tongue for that Leveling Foot may be difficult unless the stud is oriented
perpendicular to the Module frame.
5.8 > Completing the First Row
1. Lay out the next Module on the roof spaced ½" from the previously attached Module pair.
2. Attach the Leveling Foot Zep to the Module groove on top and bottom of the frame immediately
above the attachment point to the roof or attachment hardware and loosely secure the Leveling
Feet to the roof (Fig. 5.8A).
3. Install the Interlocks where the Modules join in the East-West direction on the top and bottom
of the row (Figure 5.8B). Tighten the lower Leveling Foot to the roof or attachment hardware.