Shut Down
1) Remove wire rope and hook from mobile GSE
2) Raise and stow hook against hoist bell mouth
3) Turn Indicator Switch - off
4) Push Circuit Breaker Switch – off
5) Remove mobile GSE from under the rescue
hoist
6) Detach connectors from hoist
7) Detach connectors from control box- if desired
8) Detach connector for pendant – if desired
9) Lower hanging hoist mount
a. Raise chain hoist to unload load cell pins
b. Remove load cell pins
c. Lower hanging hoist assembly
10) Remove electrical cable connectors from
hoist
11) Remove hoist