Flame Sensor Current Check 

Flame current is the current which passes through the flame from the sensor to ground. 
The minimum flame current necessary to keep the system from lockout is 0.7 microamps. 
To measure flame current, connect an analog DC microampmeter to the FC- and FC+ 
terminals. Meter should read 0.7 

µ

A or Higher.  If the meter reads “0” on scale  meter leads 

are reversed. Disconnect power and reconnect meter leads for proper polarity. 

 

 

CONTROLLER OPERATION 
Heat Mode

 

When a call for heat is received from the Switch or Thermostat supplying 24 volts to TH/W, 
the control will reset, perform a self check routine, flash the diagnostic LED for up to four 
seconds, and a pre-purge delay begins. Following the pre-purge period the gas valve is 
energised and sparks commence for the trial for ignition period. 
When flame is detected during the trial for ignition, sparks are shutoff immediately and the 
gas  valve  remains  energised.  The  thermostat  and  main  burner  flame  are  constantly 
monitored to assure the system continues to operate properly. When the thermostat is 
satisfied and the demand for heat ends, the main valve de-energised immediately. 

 

Failure to light - Lockout 

Should the main burner fail to light, or flame is not detected during the trial for ignition 
period, the control will go into lockout and the valve will be turned off immediately.  

Recovery from lockout

  

requires a manual reset by either resetting the thermostat or 

removing 24 volts for a period of 5 seconds. 
If the thermostat is still is still calling for heat after one hour the control will automatically 
reset the attempt to ignite the burner again. 

Содержание MEZZO

Страница 1: ...Page 1 of 12 Mezzo Hanging Patio Heater 29 10 10 MEZZO Hanging Patio Heater August 2010 OPERATIONS MAINTENANCE WARRANTY INFORMATION www yunca co nz ...

Страница 2: ...d Electrician to applicable Local Body and or National standards WARNING The controller uses voltages of shock hazard potential WARNING Only authorised service technicians should undertake any repairs or maintenance on this product It is recommended that the Heater has an annual maintenance check to ensure its long term correct operation WARNING Do not store or use aerosols or other flammable mate...

Страница 3: ...on Control Gas Types LPG and NG Custom prepurge and interpurge timings Pressures 2 75Kpa LPG 1 0Kpa NG Multiple tries Main Jet Sizes 1 7mm LPG 2 8mm NG Easily Assembled Main Burner Worgas Stainless Steel Atmospheric System Diagnostic LED Input Power 18 30 VAC Flame sense test pins Gas Valve 2 0A 24VAC Stainless Heater assembly 0 7µA Maximum Powder coated Frame Flame Failure Response Time 0 8 sec ...

Страница 4: ... Refer to Table 1 The following parts are NOT supplied M8 Bolts x8 for attaching Mounting Plates to support M8 Washers x8 for attaching Mounting Plates to support M8 Nuts x8 for attaching Mounting Plates to support Gas Pipe and fittings Wire and fittings for the 240 volt supply 1mm Sq wiring and fittings from the Transformer to the connection box at the vertical channel 24 volt side Maximum length...

Страница 5: ...ing Box shall be positioned to allow future maintenance and access Care is required in removing the cut outs for the wire Install the electrical wiring for the 240V supply to transformer and 24Volt system from the 24 volt side of the transformer to where the Connect Box will be mounted positioning the control switch and or thermostat in required position 24 Volt system maximum length 50 metres 1sq...

Страница 6: ... while aligning the studs with the holes Place the second washer on followed by the wing nut and tighten firmly Check the Burner is vertical Position the four dome locks over the Dome and using the bolts firmly attach the Dome to the vertical channel Fig 4 Fig 4 TESTING WARNING Initial operation must be done by a qualified Gas fitter or service technician Gas supply pressure is tested from a test ...

Страница 7: ...lem or abnormal noise it should be immediately turned off The MEZZO Hanging Patio heater should be checked and tested by authorised service technician before being used SERVICING CAUTION Only authorised service technicians should undertake any repairs or Maintenance on this product To access components there are covers that can be removed from the perforated stainless steel cylinder that surrounds...

Страница 8: ... purge delay begins Following the pre purge period the gas valve is energised and sparks commence for the trial for ignition period When flame is detected during the trial for ignition sparks are shutoff immediately and the gas valve remains energised The thermostat and main burner flame are constantly monitored to assure the system continues to operate properly When the thermostat is satisfied an...

Страница 9: ...e LED will flash on for second then off for second during a fault condition The pause between fault codes is 3 seconds Proper Electrode Location Proper location of the electrode assembly is important for optimum system performance The electrode assembly be located so that the tips are inside the flame envelope and about inch 1cm above the base of the flame Fig 6 CAUTIONS 1 Ceramic insulators shoul...

Страница 10: ... Warranty The Yunca MEZZO Hanging Patio Heater is covered by a limited two year Warranty against defects in materials and workmanship All gas components including control burner pilot assembly tubing regulator and hose are warranted for a period of one year from date of purchase Damage caused by neglect improper use acts of God theft or any other indirect incidental cause are not covered by this w...

Страница 11: ...ective Dome Horizontal Assy Vertical Channel x2 one with Cable Ties 6568PH Mounting Plate x2 Burner Assembly Insulating Box with Transformer and fuse Carrier M6 x 20mm Bolts x12 6mm Washers x12 M6 Nuts x12 0036C M6 X 26MM ALLOY FLAT WASHER DOME x6 0007D M6 S S WING NUT FOR DOME X3 Installation Instructions DATE SIGNED ...

Страница 12: ...ectrician Phone Yunca Gas PO Box 500 Dunedin 9054 Ph 03 488 4342 Email yuncagas southnet co nz Web Site www yunca co nz Cut along this line This section must be returned within 10 days of purchase YUNCA Mezzo Hanging Patio Heater WARRANTY REGISTRATION Serial No Gas type Purchase Date Purchaser s Name Purchaser s Address City Post Code Telephone Where Purchased Installed By Date Electrician Phone R...

Отзывы: