Assembly

During assembly a Temporary Guardrail will be employed.

10

 Position Trapdoor Deck on 8th rung. Ensure windlocks

on both sides are locked (see Fig 3). Ascend the tower
through the trap door of  the platform.

All components must be passed through the trap door 

or be lifted well within the footprint of the tower.

Temporary Horizontal Guardrails must be positioned 4 
rungs up from the platform during building.

Assembly

Stage 3 

11

 Fit temporary Guardrails. Locate Guardrail Frames 

and Guardrails. Ensure the interlock clips are engaged. 
Bracing pattern should follow a simple zig-zag shape (see 
insert).

12

 Ensure Intermediate Guardrails are positioned onto 

the upright above the horizontal tube, with the claws 
locked outwards as shown. Then move the platform and 
temporary Guardrails down 2 rungs.

12

13

Assembly

13

 Move other platform to the top rung of  the 2m 

Extension Frame. Ensure all Windlocks are locked. 

14

 Position upper Guardrails. Now fit toeboards correctly, 

ensuring there are no gaps large enough for objects to fall 
through and that the trap door can open and close with 
ease. (see Toeboard section). 

Your Tower is now complete 

and is ready to use. 

For increased heights refer to 
quantity schedule for additional 
packs, erect as described in 

stage 2. 

To dismantle see 

dismantling

 on page 16.

14

Содержание MiniMax

Страница 1: ...rs fitted as specified Platforms located windlocks on Handrails in place Toeboards located Refer to this checklist before using each time Check that all components are on site and that they are functi...

Страница 2: ...dismantled Safety First Wind Description Beaufort Scale Beaufort No Speed in m p h Speed in m sec Medium Breeze Raises dust and loose paper twigs snap off 4 8 12 4 6 Strong Breeze Large branches in m...

Страница 3: ...ed in total Quantity Schedule in Components Mini Max Tower to HD1004 1 83m platform Length Internal External Use Working Height m 2 8m 3 7m 5 7m 7 8m Platform Height m 0 9m 1 7m 3 7m 5 8m Description...

Страница 4: ...izontal Brace on bottom rung Ensure structure is level before tower system Use adjustable legs to level Now fit Spring Interlock clips supplied in Guardrail Pack Assemble the 4 spring locking clips as...

Страница 5: ...ern should follow a simple zig zag shape see insert 12 Ensure Intermediate Guardrails are positioned onto the upright above the horizontal tube with the claws locked outwards as shown Then move the pl...

Страница 6: ...ling ensuring that no Diagonal Braces or Stabilisers are prematurely released 1 Remove Toeboards and upper Guardrails 2 Go down to lower platform remove upper platform 3 Move lower platform and Guardr...

Страница 7: ...ck clip When moving tower lock each telescopic leg just clear of the ground unlock castors ensuring area is firm and clear of all obstructions both on the ground and above After moving check all casto...

Отзывы: