To ensure warranty coverage, this
equip ment must be commissioned
and ser viced by an authorized YORK
ser vice mechanic or a qualifi ed service
per son ex pe ri enced in chiller in stal -
la tion. In stal la tion must comply with
all ap pli ca ble codes, particularly in
regard to electrical wiring and other
safety el e ments such as relief valves,
HP cutout settings, de sign working
pres sures, and ven ti la tion re quire -
ments consistent with the amount and
type of re frig er ant charge.
Lethal voltages exist within the con trol
panels. Be fore servicing, open and tag
all dis con nect switch es.
INSTALLATION CHECK LIST
The following items, 1 through 5, must be checked be-
fore plac ing the units in operation.
1. Inspect the unit for shipping damage.
2. Rig unit using spreader bars.
3. Open the unit only to install water piping system.
Do not remove protective covers from water con-
nec tions until piping is ready for attachment. Check
water pip ing to ensure cleanliness.
4. Pipe unit using good piping practice (see ASHRAE
handbook section 215 and 195).
5. Check to see that the unit is installed and operated
within limitations (Refer to LIM I TA TIONS).
The following pages outline detailed pro ce dures to be
followed to install and start-up the chiller.
HANDLING
These units are shipped as completely assembled units
containing full operating charge, and care should be
tak en to avoid damage due to rough handling.
INSTALLATION
INSPECTION
Immediately upon receiving the unit, it should be in-
spect ed for possible damage which may have oc curred
during tran sit. If damage is evident, it should be noted in
the car ri er’s freight bill. A writ ten request for in spec tion
by the car ri er’s agent should be made at once. See
“In struc tion” man u al, Form 50.15-NM for more in for -
ma tion and details.
LOCATION AND CLEARANCES
These units are designed for outdoor installations on
ground level, rooftop, or beside a building. Location
should be selected for minimum sun exposure and to
insure adequate supply of fresh air for the condenser.
The units must be installed with suffi cient clearances
for air en trance to the condenser coil, for air discharge
away from the condenser, and for servicing access.
In installations where winter operation is intended and
snow accumulations are ex pect ed, ad di tion al height
must be provided to ensure normal condenser air
fl ow.
Clearances are listed under “Notes” in the “DI MEN -
The unit should be lifted by inserting hooks through
the holes provided in unit base rails. Spreader bars
should be used to avoid crushing the unit frame rails
with the lifting chains. See below.
Installation
Содержание YCAL0043E Series
Страница 105: ...YORK INTERNATIONAL 105 FORM 150 62 NM7 103 2 This page intentionally left blank...
Страница 127: ...YORK INTERNATIONAL 127 FORM 150 62 NM7 103 LD07832 4 LD08851...
Страница 129: ...YORK INTERNATIONAL 129 FORM 150 62 NM7 103 4 This page intentionally left blank...
Страница 131: ...YORK INTERNATIONAL 131 FORM 150 62 NM7 103 LD08855 4...
Страница 133: ...YORK INTERNATIONAL 133 FORM 150 62 NM7 103 4 This page intentionally left blank...
Страница 135: ...YORK INTERNATIONAL 135 FORM 150 62 NM7 103 LD08858 4...
Страница 137: ...YORK INTERNATIONAL 137 FORM 150 62 NM7 103 4 This page intentionally left blank...
Страница 139: ...YORK INTERNATIONAL 139 FORM 150 62 NM7 103 LD08862 4...
Страница 141: ...YORK INTERNATIONAL 141 FORM 150 62 NM7 103 4 This page intentionally left blank...
Страница 143: ...YORK INTERNATIONAL 143 FORM 150 62 NM7 103 LD08865 4...
Страница 145: ...YORK INTERNATIONAL 145 FORM 150 62 NM7 103 4 LD08867...
Страница 147: ...YORK INTERNATIONAL 147 FORM 150 62 NM7 103 4 LD08869...
Страница 149: ...YORK INTERNATIONAL 149 FORM 150 62 NM7 103 4 This page intentionally left blank...
Страница 151: ...YORK INTERNATIONAL 151 FORM 150 62 NM7 103 4 LD08872...
Страница 153: ...YORK INTERNATIONAL 153 FORM 150 62 NM7 103 LD08877 4...
Страница 155: ...YORK INTERNATIONAL 155 FORM 150 62 NM7 103 4 LD08874...
Страница 157: ...YORK INTERNATIONAL 157 FORM 150 62 NM7 103 4 This page intentionally left blank...
Страница 159: ...YORK INTERNATIONAL 159 FORM 150 62 NM7 103 LD08830 4...
Страница 161: ...YORK INTERNATIONAL 161 FORM 150 62 NM7 103 LD08833 4...
Страница 163: ...YORK INTERNATIONAL 163 FORM 150 62 NM7 103 LD08835 4...
Страница 165: ...YORK INTERNATIONAL 165 FORM 150 62 NM7 103 This page intentionally left blank 4...
Страница 167: ...YORK INTERNATIONAL 167 FORM 150 62 NM7 103 LD08844 4...
Страница 169: ...YORK INTERNATIONAL 169 FORM 150 62 NM7 103 LD08847 4...
Страница 171: ...YORK INTERNATIONAL 171 FORM 150 62 NM7 103 LD08849 4...
Страница 173: ...YORK INTERNATIONAL 173 FORM 150 62 NM7 103 This page intentionally left blank 4...
Страница 182: ...YORK INTERNATIONAL 182 FORM 150 62 NM7 103 NOTES...
Страница 183: ...YORK INTERNATIONAL 183 FORM 150 62 NM7 103 NOTES...