York MC Скачать руководство пользователя страница 6

841890-UIM-B-0612

6

FURNACE ASSEMBLY - (MC ONLY)

MC coils are supplied ready to be installed in a horizontal position. A
horizontal pan is factory installed. MC coils should be installed in all hor-
izontal applications with the horizontal drain pan side down.

For horizontal left hand applications no conversion is required to an MC
coil when used with a downflow/horizontal furnace. A mounting plate,
supplied with every coil should always be installed on the side desig-
nated as top side. See Figure 8 & 9.

FURNACE ASSEMBLY - PC

These upflow coils are designed for installation on top of upflow fur-
naces only.

If the coil is used with a furnace of a different size, use a 45° transition
to allow proper air distribution through the coil.

1.

Position the coil casing over the furnace opening as shown in Fig-
ure 10.

2.

Place the ductwork over the coil casing flange and secure.

3.

Check for air leakage between the furnace and coil casing and
seal appropriately.

Dimension “C” should be at least 2/3 of dimension “D”. See Figure 12.

CRITICAL COIL PROJECTION

The coil assembly must be located in the duct such that a minimum dis-
tance is maintained between the top of the coil and the top of the duct.
Refer to Table 6.

SECTION V: DUCT CONNECTIONS

Air supply and return may be handled in one of several ways best
suited to the installation. Upflow, horizontal or downflow applications
may be used.

The vast majority of problems encountered with combination heating
and cooling systems can be linked to improperly designed or installed
duct systems. It is therefore highly important to the success of an instal-
lation that the duct system be properly designed and installed. 

Use flexible duct collars to minimize the transmission of vibration/noise
into the conditioned space.

 FIGURE 8:  

Horizontal Right Application

 FIGURE 9:  

Horizontal Left Application

Do not drill any holes or drive any screws into the front duct
flange on the coil in order to prevent damaging coil tubing (see
Figure 12).

When installing this coil with an oil furnace, a minimum of six inches
clearance should be maintained from the top of the heat exchanger.

Refer to the heat pump add-on control instruction before installing
an add-on heat pump coil.

Furnace

Furnace

NOTICE

NOTICE

 FIGURE 10:  

Upflow Coil Installation

TABLE 5: 

Coil Projection Dimensions - PC Coils

COIL SIZE

DIMENSION “C” INCH

PC18

3-1/2

PC24

4-1/2

PC30, PC32, PC35

4-1/2

PC42, PC43, PC36, PC37

5-1/2

PC48

6-1/2

PC60

9

Use 1/2" screws to connect ductwork to unit. If pilot holes are
drilled, drill only through field duct and unit flange.

Flexible Duct
Collar

DO NOT Drill or
Screw this Flange

Field
Fabricated
Ductwork

Upflow Coil

Upflow Furnace

Secondary Drain

Primary Drain

D

C

(Min.)

Alternate
Drain Location

Содержание MC

Страница 1: ...hazardous situation which if not avoided will result in death or serious injury WARNING indicates a potentially hazardous situation which if not avoided could result in death or serious injury CAUTION...

Страница 2: ...MC Coils Only Primary Drain Secondary Drain Bottom Door Panel FIGURE 2 Component Location Coil PC Label Location Coil Access Panel Primary Drain Secondary Drain Bottom Door Panel Alternate Drain Locat...

Страница 3: ...See York bulletin 690 01 AD1V for details 20 3 8 Opening B C 3 4 Flange A 21 1 2 BOTTOM OPENING DIMENSIONS D 20 1 4 TABLE 3 Dimensions PC Coils Models Dimensions 1 Refrigerant Connections 2 Height Wid...

Страница 4: ...0 1350 42 3 1050 1350 3 1 2 1225 1575 43 3 1050 1350 3 1 2 1225 1575 48 3 1050 1350 3 1 2 1225 1575 4 1400 1800 60 62 64 4 1600 1800 5 1750 2250 For models that have factory installed TXV s take cauti...

Страница 5: ...ns and Condensate Drain Connections One mounting plate is provided with the coils COIL FLANGE FOR DOWNFLOW AND HORIZONTAL LEFT KIT INSTALLATION The coils include removable flanges to allow proper fit...

Страница 6: ...handled in one of several ways best suited to the installation Upflow horizontal or downflow applications may be used The vast majority of problems encountered with combination heating and cooling sys...

Страница 7: ...n it should be piped to a loca tion that will give the occupant a visual warning that the primary drain is clogged If the secondary drain is not used it must be capped DO NOT use TeflonTM tape pipe do...

Страница 8: ...il using a portable manometer and static pressure tips To prepare coil for static pressure drop measurements the system should have been recently operational in cooling mode Drill 2 holes one 3 after...

Страница 9: ...TXV Bulb positioned correctly Is Bulb Insulated Is Equalizer Line connected FIGURE 16 Drain Traps Secondary Primary 3 Min Were the primary and secondary drains trapped correctly FIGURE 17 Location of...

Страница 10: ...change without notice Published in U S A 841890 UIM B 0612 Copyright 2012 by Johnson Controls Inc All rights reserved Supersedes 841890 UIM A 0412 York International Corp 5005 York Drive Norman OK 73...

Отзывы: