2. Transportation, Storage and Installation
2-7
TI 32P01J10-01EN
2.5.1
Installation on Floor
The installation method varies with the type of the floor and building.
• After unpacked, be careful not to put any impact until the equipment is fixed to the floor to
prevent it from falling to the floor.
• Install devices as specified in the plans. Check the position of front and back panels of the
cabinet.
Avoid physical shock. Never use hammers.
• Fix each equipment to the floor.
The explanation below shows how to fix devices on different types of floors.
Concrete Floor
Clamp the equipment to the floor using anchor bolts. It is recommended to use M12 bolts and
3200 N•cm (320 kgf•cm) tightening torque.
Equipment
Anchor bolts
F020501.ai
Figure Using Anchor Bolts
Steel Floor
Clamp the equipment to the floor using clamp bolts.
After cabling through the riser duct, fill the duct with rubber sponges and seal the top with putty.
Equipment
Steel floor
Clamp bolt
F020502.ai
Duct
Riser
Figure Using Clamp Bolts