EtherLeap User’s Manual
Section 2
Installation
2.1 Introduction
Please review the entire manual before powering up or deploying any EtherLeap.
The EtherLeap comes pre-configured from factory for point-to-point layer-2 bridging operation.
NOTE
:
It is strongly recommended that you configure and test the units prior to deploying them in the
field. Set up a “mini-network” that resembles your actual configuration as close as possible.
By using such a mock-up, troubleshooting potential problems will be much easier than if you
already installed the equipment in the field. Read through this entire Section 2 to understand
how to install the hardware. To configure the EtherLeap , read Section 3.
2.2 DC
Power
Injector
The Cat 5 DC Power Injector is not in a waterproof enclosure and must be protected from the weather. It
can be permanently mounted to a surface using the double stick tape found on the back of it.
2.3 Power
Supply
The Ether Leap kit comes with a 110/220 VAC to 48 VDC power supply that has a standard barrel plug
[center pin positive (+) tip and outer ring negative (-)].
2.4 LED
One red LED is present on the back of the EtherLeap (see Figure 2.1):
•
The red LED stays on when the unit is operating correctly
•
The red LED flashes when there is a fault
Figure 2.1 – EtherLeap LED
Red LED
Version 1.0
Page 3