Antai Solar Mounting Rack Compliance to AS Code 1170 

4

II. Planning the Module Area 

 

1.  Number of modules in the vertical direction × module height (please check also the installation manual 

of the manufacturer of the solar panel) 

2.  Number of module in horizontal direction× (module width+17mm)+32mm   
3.  Horizontal spacing of the Fix Foot up to 2m

1

 

4.  Vertical spacing of the Fix Foot-approx 1/2 to 3/4 module height 
5.  Distance between the modules:17mm 
 

1

Caution: Installations that are exposed to the wind or are located on the edge or corners of the roof make 

it necessary to leave smaller spacing. 
 

III. Determination of Fixing Centres   

1, Determine the wind region for the site of installation. Refer to AS1170.2:2002 Figure 3.1 for wind region A, 

B, C, or D within Australia.   

2, Determine the height of the installation above ground level   
3, Determine the spacing of rail fixings based on table. 
4. For Installations in Northern Territory solar panels are not to be placed within 1.2m of roof edges.   
   
Installation conditions:   

  Wind loads to AS1170.2:2002   

  Wind average recurrence interval of 500 years   

  Wind terrain category 2.   

  Shielding and topography multipliers, Ms and Mt taken as unity.   

  Racks mounted on roofs of enclosed buildings of nominal rectangular shape.   

  Panel slopes up to 45° from horizontal.   

  Maximum solar panel length of 2.0m   

  Maximum solar panel width of 1.2m   

  Minimum of 2 rails supporting each panel   

  Maximum solar panel weight of 15kg/m

2

 

  Roof structure to be checked and certified as suitable for applied rack loads prior to installation   

  Solar panels to be certified by manufacturer as able to resist wind loads in accordance with 

AS1170.2:2002 

 
 
 
 
 
 
 
 
 
 

Содержание Antai Rail?

Страница 1: ...tallation Manual Antai Rail Solar Mounting System Flat Roof Solution Version 1 1 Office Add 508 North Tower Guangxia Building Huli Torch Hi tech Zone Xiamen China Factory Add Guanshan Industrial Park Changtai County Zhangzhou China Tel 86 592 3852509 Fax 86 592 3852618 Website www antaisolar com ...

Страница 2: ...engineered new innovative product designed with experienced engineers to the speed the installation Benefits of Antai Flat Roof Mounting System Easy Installation Diversified Application High Accuracy Choice Quality Engineered to highest standards Maximum Lifespan Guaranteed durability Technique Parameter Installation site pitched roof Roof Slope up to 45 Wind load To AS Code1170 2 2002 PV module F...

Страница 3: ...components Part name picture Part name picture Antai Rail Fix Foot Splice Adjustable Leg Strut Inter Clamp with T module End Clamp with T module T module hexagon socket bolt M8 12 30 50 70 Klamp Lock 700 Klamp Lock 406 Note The quantity of requested components depends on the system you ordered ...

Страница 4: ... for wind region A B C or D within Australia 2 Determine the height of the installation above ground level 3 Determine the spacing of rail fixings based on table 4 For Installations in Northern Territory solar panels are not to be placed within 1 2m of roof edges Installation conditions Wind loads to AS1170 2 2002 Wind average recurrence interval of 500 years Wind terrain category 2 Shielding and ...

Страница 5: ... to steel and timber respectively screw through to 1 2mm Min BMT steel or 50mm Min embedment into timber Wind Region to AS 1170 2 2002 Height Above Ground Meters Wind Region A Wind Region B Wind Region C Wind Region D 5 938 575 353 N S 10 771 474 318 N S 15 697 429 N S N S 20 657 405 N S N S Note N S denotes not suitable TPI Threads per inch In Northern Territory solar panels are not to be placed ...

Страница 6: ...pacing table on the previous page Shim the Fix Foot with rubber Fix the Fix Foot to the rafter using 2 12g screws as notes in the fixing table 2 Fix the Fix Foot to the rafter according to your plans Installation of Klamp Lock on Metal Roof 3 Use our Klamp Lock to clip the metal roof tightly and place Fix Foot on Klamp Lock and connect them by tightening M8 20 Bolt ...

Страница 7: ...ule use M8 30mm bolt 5 Base rail installation position the first frame rails for each row and fasten them temporarily to the roof cladding using a cord Tighten the Allen bolts on the T module that are used to fasten the fix foot 6 Install the Leg strut put the leg strut into the pedestal and fasten them by M8 70mm bolt 7 Put the Leg tube into the Leg strut and adjust to the planed length then usin...

Страница 8: ...sing the Allen key Now slide the next rail segment into the splice Tighten the second M8 bolt The connection is finished 11 For each use of the T module You must make sure that the thread of the screws does not project through the lower side of the T module max flush Position the T module in the rail channel and fasten it loosely with2 to 3 turns of the screw The screws can still be freely moved i...

Страница 9: ... through the end clamp when installation step12 has been correctly performed 14 Slide the pre assembled inter clamp into the rails from above place it firmly against the module and fasten loosely 15 Now slide the next module against the previously installed module and tighten the inter clamp using the Allen key Take care that the anti slip protection sits in the rail channel of the lowest row of r...

Страница 10: ...odule in the row on the rails with the first row of modules take care that the anti slip protection sits properly in the rail channel and fasten the last inter clamp and the end clamp using the Allen key 17 Leg Strut and fix foot can be adjusted 18 AnTai rail grounding system ...

Страница 11: ...rformed in accordance with Antai s written installation instructions or if the Product has been modified repaired or reworked in a manner not previously authorized by Antai IN WRITING or if the Product is installed in an environment for which it was not designed Antai shall not be liable for consequential contingent or incidental damages arising out of the use of the Product by Purchaser under any...

Отзывы: