Commissioning
3–6
152379 Rev B
Confirm DC Operational Parameters
1. Verify the Inverters PV Settings.
2. Make any necessary changes.
3. Record these values.
4. Once you finish these tasks, go back to the GUI Commissioning Procedure
and click on the check box to indicate the task is complete. Go to the next step
by clicking on the "
N
EXT
" button.
Confirm Power Tracker Configuration Operational Parameters
1. Verify the inverter’s Power Tracker Configuration.
2. Make any necessary changes.
3. Record these values.
4. Once you finish these tasks, go back to the GUI Commissioning Procedure
and click on the check box to indicate the task is complete. Go to the next step
by clicking on the "
N
EXT
" button.
Verify Door Interlock Functions
1. Open the front door of the Main Inverter Enclosure and verify a door interlock
fault is triggered (0070 “INTERLOCK ACTIVATED”).
2. Bypass the switch by pulling it out into the service position.
3. Clear the fault.
4. Once you finish these tasks, go back to the GUI Commissioning Procedure
and click on the check box to indicate the task is complete. Go to the next step
by clicking on the "
N
EXT
" button.
Matrix Test
1. Confirm that the
O
N
/O
FF
Switch (S3) in the
O
FF
position.
1. From the GUI or front panel, select Matrix test from the Goal State menu.
2. Verify the six yellow LEDs on the IGBT driver board are blinking. The
blinking yellow LEDs are an indication that the IGBT driver board is gating
correctly.
3. If any of the six yellow LEDs on the IGBT driver board are not blinking, refer
to the Matrix Gate Faults listed on page 4–8 of the “Troubleshooting” Section.
4. To stop the test, select Goal state from the GUI or Front Panel and choose
Shutdown.
5. Close the door and clear any alarms.
6. Once you finish the Matrix Test, go back to the GUI Commissioning
Procedure and click on the check box to indicate the task is complete. Go to
the next step by clicking on the "
N
EXT
" button.
Содержание PV100S-208
Страница 1: ...PV100S 100 kW Grid Tied Photovoltaic Inverter Operation and Maintenance Manual PV100S 208 PV100S 480...
Страница 2: ......
Страница 3: ...s PV100S 100 kW Grid Tied Photovoltaic Inverter Operation and Maintenance Manual...
Страница 8: ...vi...
Страница 14: ...xii...
Страница 22: ...xx...
Страница 78: ...2 38...
Страница 86: ...3 8...
Страница 104: ...5 8...
Страница 109: ...Appendix A Schematics 152379 Rev C A 5 Figure A 1 Electrical Diagram sample...
Страница 110: ...Schematics Appendix A A 6 152379 Rev C Figure A 2 PV100S 480 Schematic for Main Power Distribution 152316 E1...
Страница 111: ...Appendix A Schematics 152379 Rev C A 7 Figure A 3 PV100S 480 Schematic for Control Power Distribution 152316 E2...
Страница 112: ...Schematics Appendix A A 8 152379 Rev C Figure A 4 PV100S 480 Schematic for Converter Control Unit 152316 E3...
Страница 113: ...Appendix A Schematics 152379 Rev C A 9 Figure A 5 PV100S 208 Schematic Main Power Distribution 152376 C1...
Страница 114: ...Schematics Appendix A A 10 152379 Rev C Figure A 6 PV100S 208 Schematic for Control Power Distribution 152376 C2...
Страница 115: ...Appendix A Schematics 152379 Rev C A 11 Figure A 7 PV100S 208 Schematic for Converter Control Unit 152376 C3...
Страница 116: ...Schematics Appendix A A 12 152379 Rev C This page intentionally left blank...
Страница 120: ...Warranty and Return WA 4 152379 Rev C...
Страница 123: ......