22
CONDENSATE, GAS & WATER
CONNECTIONS
CONDENSATE, GAS & WATER CONNECTIONS
6-720-611-730b (12.05)
CONDENSATE CONNECTION:
The condensate pump (G) fills up and periodically
discharges through the flexible condensate pipe
(H) 200mm to 1500mm from floor level. After this
point the condensate continues down the 21.5mm
plastic pipe to the outlet using gravity.
Route and secure condensate waste pipe (H)
to prevent kinking or restriction.
Cut off any excess pipe (H).
Fit the condensate waste pipe (H) to adaptor
(K) and secure with clip (J).
Connect adaptor (K) to 21.5mm plastic pipe
and terminate into an internal waste trap.
(See Pre-Installation section for condensate
pipework running from the adaptor (K) to the
discharge outlet).
Never terminate or discharge into any open
source, including; sink, bath, shower, bidet,
toilet etc.
Note: any external condensate pipework should
be protected with weather resistant insulation to
help prevent freezing.
CAUTION: ISOLATE THE MAINS GAS AND
WATER SUPPLY BEFORE STARTING ANY
WORK AND OBSERVE ALL RELEVANT
SAFETY PRECAUTIONS.
GAS AND WATER CONNECTIONS:
Remove the transit bungs (L) from the gas &
water connections (A, B, C, D & E) on the boiler
and mounting frame.
Note: that surplus water may be present due to
factory testing.
Ensure the area is clear of debris and
manoeuvre the boiler rear wheels onto the outer
rails of the mounting frame (F).
Take care when moving the boiler to position
the front wheels onto the rails and align the
gas/water connections and the flue.
Secure boiler to mounting frame (F) with screw
(M)
Place the 3 larger valve sealing washers (shown
shaded) onto valves A,C & E.
Place the 2 smaller valve sealing washers onto
valves B & D.
Ensure all pipework is clean.
Tighten the compression fittings to secure:
A - CH flow (22mm).
B - DHW flow (15mm).
C - Gas inlet (22mm).
D - Mains water inlet (15mm).
E - CH return (22mm).
Max. 1500mm
H
Min. 200mm
G
H
J
K
H
F
G
E
D
C
B
A
L
M