4
P-clamp installed 14” from ends
of sheathed cables, next to zip
tie on sheathed cables
7. Run the replacement sheathed cables through the feed arm.
8. Connect the four coax cables running through the feed arm to the
to the LNB. The coax cables can be connected in any order. Tighten
the cables until fingertight, and then use a 7/16” wrench to tighten a
quarter turn more.
9. Slide the LNB into the feed arm, and re-install the two screws
(removed earlier) through the underside of the feed arm and LNB.
Tighten.
10. Slide the LNB guard up the feed arm and over the LNB. The front of
the LNB guard should be ~½” in front of the LNB and should not be
touching the LNB.
11. Install the four bolts through the four holes in the LNB guard. Thread a
nut onto each bolt, and tighten.
12. Connect the other ends of the sheathed cables to coax ports A–D on
the top of the turret. Tighten each cable until fingertight, and then use a
7
/
16
” wrench to tighten a quarter turn more.
13. Place the p-clamp on the
sheathed cables, and make
sure the hole in the p-clamp is
positioned above the cables. The
p-clamp must be 14
inches
from
the ends of the sheathed cables.
This point on the cable may
already be marked by a zip tie,
mark, or tape.
14. Align the hole in the p-clamp
with the hole in the lift arm.
Install the screw through the
p-clamp and lift arm, and
tighten.