Installation
5.3 Assemble machine
5
5.2.1
Installation preparation
•
Open the packaging unit prior to the assembly and remove the machine from the
packaging unit.
•
The attachment screws must be at hand.
5.2.2
Operating media / Auxiliary media / Tools
The following are required for installation of the machine:
•
One set of spanners
•
One torque wrench
•
One set of screwdrivers
•
Screw securing agent (e.g. Loctite ® 243)
•
Screws which are at least have a property class of 8.8
5.3
Assemble machine
5.3.1
Assembly with base body
L
The Pick-o-Mat assembly machine is delivered, fully assembled mechanically, on a base
frame. Assembly only entails setting up and screwing the base frame to the floor at the
installation site.
The module needs to be aligned horizontally with the levellers during the setup.
5.3.2
Assembly without base body
L
The Pick-o-Mat assembly machine is delivered fully assembled mechanically. Assembly
only entails setting up and screwing the base frame to the floor at the installation site.
Installation conditions:
•
Drill pattern and installation perforations of the base plate according to catalogue spe-
cifications
•
Evenness of the base plate < 0.1 mm
1. Place the module on the base plate while observing the transport regulations and
align according to the boreholes and pin holes.
2. Precentre both parallel pins and then drive in the first parallel pin 1/3 of its length.
3. Screw in the fixing screws and tighten slightly.
4. Drive in the second parallel pin completely, followed by the first parallel pin.
5. Tighten the fixing screws firmly in a diagonal pattern with a torque wrench.
6. Remove the yellow closing plug of the gear ventilation.