7 Commissioning
83055902 1/2019-04 La
35-84
7.2 Adjusting the burner
DANGER
Risk of electric shock
Touching the ignition device can lead to electric shock.
Do not touch ignition device during the ignition process.
During commissioning check:
flame signal [ch. 7.1.1],
suction resistance or flow pressure of oil pump [ch. 5.1],
mixing pressure [ch. 7.1.2].
1. Start the burner
A plug switch can be used to switch the stages during commissioning (Order No.
130 103 15 012).
Heat demand from the boiler controller required.
Open fuel shut off devices.
Unplug 4 pole connection plug.
Switch on voltage supply.
Illuminated push button lights up red.
Press illuminated push button for 1 second.
Burner starts in accordance with the program sequence and stops at stage 1
[ch. 3.3.4].
Set pump pressure for stage 1
The pump pressure must be set according to the nozzle selected [ch. 4.2].
Check pump pressure at pressure gauge.
Set pressure using pressure regulating screw
1
:
increase pressure: clockwise rotation,
decrease pressure: anticlockwise rotation.
1