Before Installing Boiler

1a

Installation must comply with:

• State, provincial and local plumbing,

heating and electrical codes.

• Regulations of serving utilities.
• National codes where applicable.

Before selecting boiler location:

• Check for nearby connections to:

– fuel supply
– electrical power
– system water or steam piping
– venting systems - see page 23
– combustion and ventilation air supply - see

“Provide combustion and ventilation air
supply openings” below

• Check area around boiler for and remove any

combustible materials, gasoline and other
flammable vapors and liquids.

Failure to keep boiler area clear and free of
combustible materials, gasoline and other
flammable liquids and vapors can result in severe
personal injury, death and substantial property
damage.

Provide combustion and ventilation
air openings:

Do not install an exhaust fan in boiler room.
Adequate combustion and ventilation air must be
provided to assure proper combustion and
prevent possibility of flue gas leakage and carbon
monoxide emissions, causing severe personal
injury or death.

Opening sizes must comply with state, provincial
or local codes. In their absence, use the following
when boiler is in a confined room:
• Provide two permanent openings in boiler

room - one within 12 inches of ceiling, one
within 12 inches of floor. Minimum dimension
of each opening - 3 inches.
- When all air is taken from within building,

each opening should be at least one square
inch/1,000 Btuh boiler input and freely
connect with areas having adequate
infiltration from outside

- When all air is taken from outdoors, each

opening should connect directly or by ducts
from outdoors or crawl or attic spaces that
freely connect with outdoors and sized as
listed below:
- through outside wall or vertical ducts - at

least one square inch/4,000 Btuh boiler
input

- through horizontal ducts - at least one

square inch/2,000 Btuh boiler input

- where ducts are used, they should be same

cross-sectional area as free area of
openings they are connected to

- compensate for louver, grille or screen

blockage when calculating free air
openings. Refer to their manufacturer’s
instructions for size. If unknown, use:
- wood louvers - 20-25% free air
- metal louvers or grilles - 60-75% free air
- screens - not less than 1/4 inch mesh
Lock louvers in open position, or interlock
with equipment to prove open before
boiler operation.

Part No. 550-141-705

3

Figure 1 Combustion and Ventilation Air

Openings Boiler Room Below Grade

Figure 2 Combustion and Ventilation Air

Openings Boiler Room Partially or Completely

Above Grade

GRADE

GRADE

Grating – Min.
12" above avg.
snowline

Louver  – Min.
12" above avg.
snowline

Note:
Duct size
equal to total
louver area

Areaway

Louver

Boiler room
floor

Boiler room
floor

Note:
Size of areaway
and grating to be
equal to or
greater than total
louver area.

Содержание 1078

Страница 1: ...substantial property damage Part No 550 141 705 0600 78 78 Boiler For Gas Light Oil Gas Light Oil Fired Burners Boiler Manual Installation Start Up Maintenance Parts Installer Leave all documentation received with boiler and burner with unit for future reference User Boiler and burner must be installed and serviced by a qualified service technician ...

Страница 2: ... of various risk levels or to important information concerning the life of the product Indicates presence of hazards that will cause severe personal injury death or substantial property damage if ignored Indicates presence of hazards that can cause severe personal injury death or substantial property damage if ignored Indicates presence of hazards that will or can cause minor personal injury death...

Страница 3: ...n 12 inches of floor Minimum dimension of each opening 3 inches When all air is taken from within building each opening should be at least one square inch 1 000 Btuh boiler input and freely connect with areas having adequate infiltration from outside When all air is taken from outdoors each opening should connect directly or by ducts from outdoors or crawl or attic spaces that freely connect with ...

Страница 4: ...ewall vent pipe 18 inches doublewall vent pipe refer to vent pipe manufacturer s recommendations for vent pipe clearances Lay a foundation if needed Floor construction and condition must be suitable for weight of boiler when filled with water See page 31 for boiler weight water weight A level concrete or brick foundation is required when A floor could possibly become flooded Non level conditions e...

Страница 5: ... rollers under steel skid angles to roll boiler 3 Place boiler in final position Center boiler on foundation if used 4 Level boiler Shim under skid angles if necessary 5 Cut off cables Cables are not intended for long term usage Cables may corrode inside boiler weakening their lifting strength Failure to remove cables can result in severe personal injury death or substantial property damage 6 Insp...

Страница 6: ...t 1 intervals and push together Do not stretch Do not pre cut rope Gas tight seal must be maintained to prevent possibility of flue gas leakage and carbon monoxide emissions causing severe personal injury or death 3 Remove any grit from port machined surfaces with clean rag Do not use petroleum based cleaning or sealing compounds in boiler system Severe damage to system components can result causi...

Страница 7: ......

Страница 8: ... Position 1 2 sealing rope in groove Overlap ends at least one inch c Install burner mounting plate Use 1 2 washers and nuts Install observation port assemblies on front and back sections 1 Install front observation port assembly a Apply 1 8 continuous bead of sealing rope adhesive in groove on observation port b Position 3 8 sealing rope in groove Overlap ends at least one inch c Secure assembly ...

Страница 9: ......

Страница 10: ...assembly See Figure 9 a Lay hood on floor with flanged side up b Wipe flanged surface with clean rag to remove dirt and oil c Apply double faced tape to flanged surface d Apply rope to tape beginning on one side of open end of hood leaving 1 4 extending past edge Around corners bend rope do not cut Do not stretch rope Do not pre cut rope Gas tight seal must be maintained to prevent possible flue g...

Страница 11: ...not to distort hood d Tighten six 5 16 x 1 flanged bolts and flanged nuts on flue collar to 30 35 in lbs Overtightening bolts in flue collector hood assembly will cause gasket material to extrude causing possible flue gas leakage and carbon monoxide emissions resulting in severe personal injury or death 4 Check gas tight seal of flue collector hood and flue collar Gas tight seal must be maintained...

Страница 12: ......

Страница 13: ...g per Table below Flow at higher velocities than shown in Table below for pipe size can damage boiler causing substantial property damage b Locate circulator in supply piping c For return piping use full diameter pipe for 10 times that diameter before making any reduction For example a 4 inch return should not be reduced any closer to boiler return tapping than 40 inches d Install system blow off ...

Страница 14: ......

Страница 15: ...izer J pipe size b Install system drain valve in lowest part of return piping close to boiler ASME size requirements are shown in Table page 13 c Connect cold water fill piping as shown in Figure 14 Also shown are recommended valves and water meter if used Water meter will detect added makeup water indicating leaks in system Part No 550 141 705 15 Based onASHRAE Handbook recommendations allowing 1...

Страница 16: ......

Страница 17: ......

Страница 18: ......

Страница 19: ......

Страница 20: ......

Страница 21: ......

Страница 22: ......

Страница 23: ......

Страница 24: ... boiler controls 1 Install all wiring in compliance with National Electrical Code ANSI NFPA 70 Any additional national state or local codes 2 Follow burner manual and wiring diagram found in burner information packet 3 Use 14 ga wire for operating and safety circuit wiring 4 Where burner motor voltage differs from control voltage supply proper voltage to each Size fused disconnect s and conductors...

Страница 25: ...bustion test equipment to assure proper operation Do not fire boiler without water Sections will overheat damaging boiler and resulting in severe property damage 1 Lock open breeching damper 2 Refer to burner manual for start up and service 3 Let burner advance to high fire Heat boiler to design conditions 4 Using combustion test equipment adjust burner for a 12 1 4 C02 for No 2 fuel oil 0 smoke b...

Страница 26: ...atment is needed water boilers only Do not use petroleum based cleaning or sealing compounds in boiler system Severe damage to system components can result causing substantial property damage Continual make up water will reduce boiler life Minerals can build up in sections reducing heat transfer overheating cast iron and causing section failure For unusually hard water areas or low pH conditions l...

Страница 27: ... 1 8 8 42 1 2 27 1 2 34 3 8 35 1 2 678 2 4 2 4 2 3 2 3 34 1 8 8 42 1 2 34 1 2 41 3 8 42 1 2 778 2 4 2 4 2 3 2 3 41 1 8 10 41 1 2 41 1 2 48 3 8 49 1 2 878 2 4 2 4 2 3 2 3 48 1 8 10 41 1 2 48 1 2 55 3 8 56 1 2 978 2 4 2 4 2 3 2 3 55 1 8 10 41 1 2 55 1 2 62 3 8 63 1 2 1078 2 4 3 4 2 3 2 3 62 1 8 27 1 8 10 41 1 2 62 1 2 69 3 8 70 1 2 1178 2 4 3 4 2 3 2 3 69 1 8 34 1 8 10 41 1 2 69 1 2 76 3 8 77 1 2 12...

Страница 28: ... Gas Light Oil Gas Light Oil Fired Burners Data and Dimensions 15b Part No 550 141 705 28 Front Back Side Intermediate Minimum for heater removal 3 NPT return W Boiler section length 4 NPT supply outlets 3 NPT return Water line ...

Страница 29: ... Installation Start Up Maintenance Parts Part No 550 141 705 29 Parts 16a B A C O N E G F D J K L P Q K M P I H ...

Страница 30: ...d C 11B340 Flue Collector Hood D 11B341 Flue Collector Hood E 11B351 Flue Collector Hood Hardware Kit includes flat stitched sealing rope 11B342 double faced tape flue collar gasket collector hood gaskets holddown clips hardware K Collector Hood Gasket Kit includes flue collector hood gasket flue 11B311 collar gasket flat stitched sealing rope and double faced tape L Flue Collector Hood End Cap 11...

Страница 31: ...l or H for boiler only for use with approved burners Add prefix A to designator for factory assembled 78 ABL 478 Substitute P for B for fire tested package unit PL 478 Substitute S for steam W for water For T intermediate section s and tankless heater s add suffix number required TIH for T intermediate section s with cover plate s only add suffix number required TIP Burner input based on maximum o...

Страница 32: ...Part No 550 141 705 0600 32 ...

Отзывы: