IMPORTANT:
WHEN PLACING SHORT STEM TRACK ROLLERS INTO THE #2 GRADUATED
END HINGES AND HIGHER, THE SHORT STEM TRACK ROLLER GOES INTO HINGE TUBE
FURTHEST AWAY FROM SECTION.
Center
hinge(s)
#1 Graduated
end hinge
Short stem track roller
Lower hinge leaf
#2 Graduated end hinge
(roller inserted into tube
furthest from section)
1/4”-20 x 11/16” Self
drilling screw locations
Single Graduated End Hinges
Endcap
Endcap
Short stem
track roller
Center
hinge(s)
Dimples
Dimples
Long stem track roller
Lower hinge leafs
#2 Graduated end
hinges (roller
inserted into tubes
furthest from section)
1/4”-20 x 11/16” Self
drilling screw locations
Endcap
Endcap
Center
hinge(s)
Double Graduated End Hinges
Center
hinge(s)
#1 Graduated
end hinges
Long stem
track roller
Attaching Strut To Bottom Section
7
NOTE:
Depending on the size of your door, your bottom section may require one or more
struts.
NOTE:
Referring to the Bottom Section Strutting Schedule below to determine how many
struts your bottom section is needed to be installed.
Using sawhorses, lay the bottom section on a flat smooth surface. Referring to the Bottom
Section Strutting Schedule below, determine how many strut(s) your bottom section is
needed to be installed.
NOTE:
If your bottom section doesn’t require a strut to be installed, then skip this step.
Center the strut onto the bottom section surface either up against the bottom of the hinges or
along the top edge of the bottom corner brackets. Center the strut side to side on the section.
Secure strut to the section using 1/4” - 20 x 7/8” self drilling screws at each end and at each
center hinge(s) / dimple location(s), as shown.
Bottom Section Strutting Schedule
Door Height
# Of Sections
Door Width
12’0” - 14’0”
15’0” - 18’0”
20’0”
6’6” - 10’0”
4 - 5
2” Strut, Top of Bottom section
3” Struts, Top of
Bottom section
and Bottom of
Bottom section
10’3” - 14’0”
6 - 7
2” Strut, Top of
Bottom section
3” Strut, Top of
Bottom section
Single Endstiles:
Endcaps
Typical section
Strut
1/4”-20 x 7/8” Self drilling screw locations
Double Endstiles:
Endcaps
Typical section
Strut
1/4”-20 x 7/8” Self drilling screw locations
Center hinge(s)
Center hinge(s)
Typical bottom corner brackets
Strut
(2) 1/4”-20 x 7/8”
Self drilling screws
Bottom portion of bottom section
Attaching Top Fixtures To Top Section
8
NOTE:
Depending on your door, you may have Top Fixture Bases and Top Fixture Slides or
you may have Top Fixture Assemblies. Refer to Package Contents / Breakdown of Parts, to
determine which Top Fixtures you have.
Using sawhorses, lay the top section on a flat smooth surface. Referring to the Top Section
Strutting Schedule below, determine if your top section is required for strutting.
Top Section Strutting Schedule
Door Height
# Of Sections
Door Width
6’0” - 14’0”
15’0” - 20’0”
6’6” - 14’0”
4 -7
2” Strut, Top of Top
section
3” Strut, Top of Top
section
IF YOU HAVE TOP FIXTURE ASSEMBLIES:
Place and center the strut onto the top section
surface along the top of edge of the top section. Center the strut side to side on the section.
Secure strut to the section using 1/4” - 20 x 7/8” self drilling screws at each end and at
each center hinge(s) / dimple location(s). Next, align the top fixture base below the strut and
even with the edge of the section. The slotted half of the top fixture base should be facing
upwards. Secure the top fixture to the top section through the end cap using (4) 1/4” - 20
x 11/16” self drilling screws. Insert short stem track roller into top fixture slide. Repeat for
other side.
NOTE:
If needed, ensure the top fixture slides are able to slide back and forth along the top
fixture base. If needed, loosen the (2) 1/4” - 20 flange hex nuts.
The fixture will be tightened and adjusted later, in step, Adjusting Top Fixtures.
(4) 1/4”-20 x 11/16”
Self drilling screws
(2) 1/4”-20 Flange
hex nuts
Short stem
track roller
End
cap
Top
section
Strut
Top section
(2) 1/4”-20 x 7/8”
Self drilling screws
IF YOU HAVE TOP FIXTURE BASES AND TOP FIXTURE SLIDES:
Loosely secure the top
fixture slide and the “L” reinforcement bracket (if applicable) to the top fixture base using (1)
5/16” - 18 x 3/4” carriage bolt and (1) 5/16” - 18 hex nut, as shown. Repeat for other top
fixture assembly(s).