Hydroxzone Ozone Generator
2.5.4. Connect the polybraided hose to the barb on the side of the Hydroxzone Ozone
Generator. (see Figure 2.6).
2.5.5. For flooded installations or where the Hydroxzone is installed below 400mm above
the highest point of the filter system, two (2) check valves and a drain must be
installed as follows: (see Figure 2.7)
I. Cut the braided supply tube a minimum of 600mm from the Hydroxzone unit.
II. Install the supplied ¼” barb Tee between the 2 sections of supplied polybraided
hose, with one end of the Tee vacant and pointing to the ground
III. Cut the polybraided hose supply line approximately 200mm further on the
Venturi Injector side of the ¼” barb Tee piece, and install a check valve with the
concave shape facing the direction of the Dynamic Venturi Injector, ensuring the
flow of air from the Hydroxzone unit to the Dynamic Venturi Injector.
IV. Cut the polybraided hose to length, ensuring a length of 200-300mm of braided
supply hose is available to make a drain off the ¼” barb Tee piece
V. Take the 200-300mm piece of polybraided hose supply and cut it in half
VI. Install the second check valve between the 2 pieces of cut supply hose
VII. Connect the 200-300mm piece of hose with check valve installed, and connect
to the base of the Tee – ensuring that the concave shape is facing toward the
vacant end of tube (Figure 2.7). Ensure this drain tube is pointing to the ground.
This will ensure water is able to drain from the supply tube.
VIII. Connect the other end of the braided supply tube to the Dynamic Venturi
Injector’s open nipple. Secure with a black plastic clip.
2.6 Connecting polybraid hose to Hydroxzone