BUILDING A BASE

When thinking about where the building and base is going to be constructed: Ensure that there will be access to all sides for maintenance work and 

annual treatment.

TYPES OF BASE

- Concrete 75mm laid on top of 75mm hard-core.

- Slabs laid on 50mm of sharp sand.

Ensure the base is level and is built on firm ground, to prevent distortion.  Refer to diagrams for the base dimensions,  The base should be slightly 

smaller than the external measurement of the building, i.e. the cladding should overlap the base, creating a run off for water. It is also recommended 

that the floor be at least 25mm above the surrounding ground level to avoid flooding.

Step 6

Use 30mm  screws to fix each 
cover trim

12 x 30mm screws

1

7

7

Step 7

20x 30mm Screws

Fix the roof panels on either side 
as shown in diagram.  

Fix panels into position using  
30mm screws from the top of the 
panel, straight into the framing
Pre drill holes before hand.
Ensure the larger over hang on 
both panels are facing each 
other at the top point.

9

6

Fix the roof eaves to the roof panel 

using 30mm screws. Make sure the 

roof eave is flush with the edges. 

Step 8

Lay the felt sheet over the roof in one 
strip, making sure to leave an equal over 
hang at the front and back. Leave a 
50mm overhang at the sides.

Fix using felt tacks at 100mm intervals

30 x felt tacks

Felt 

tacks 

13

Step 9

Fix fascias and finials using 

40mm screws. Pre drill holes to 

avoid splitting. Ensure to trap 

the felt between the fascia and 

building.

8x 40mm screws

10

8

It is ESSENTIAL that you apply wood 

treatment immediately after the building 

has been assembled.

40mm 

screw