Rev. 1.1
Assembly Instructions - Full-Jet Valve VMS-05
Page 9 of 25
Walther Systemtechnik GmbH
– D 76726 Germersheim
Telefon: +49 (0)7274-7022-0 Telefax: +49 (0)7274-7022-91
http://www.walther-2000.de
5 Initial Start-up
5.1 Mounting and Installation
Connect the
VMS-05 Hand Dosing Valve
with a pressured container or a pump via the material connection
(4). Connect the micro-switch (15) with a pilot valve (magnetic valve or time control or other). Adjust material
pressure at the pressured container or the pump (max. 20bar). When you now operate the micro-switch,
material will be discharged from the nozzle.
The
VMS-05 Special Design
valves can be installed in any position. The distance to the application area
depends on the desired application image.
An intermittent operation of the device will cause certain vibrations. Therefore make sure that the device is
safely and securely fixed and installed. The device comes with two borings of 5mm diameter in the valve
body which can be used for a solid installation. Try to avoid extremely large vibrations (transfer from
machines to valve).
5.2 Hose Mounting
Standard
Three functional hoses will connected as follows:
1.
Control air (black) to plug-in nipple (open 7
SA
)
2.
Control air (black) to plug-in nipple (close 7
SZ
)
3.
Material (transparent) to 1/4"-connection (4)
Special Design
Two functional hoses will be connected as follows:
1.
Control air to M5-connection (21.0.0)
2.
Material to 1/4"-connection (21.20)
Control air
Material
Control air
open
Material
Control air
close