Annex: STS 40nn and STS 10nn with clamping system 

  Proper status of coupling has to be checked before every loading and every transport. 

  Separating of wagons is strictly forbidden. 

It is strictly forbidden to rearrange the wagon arrangements of STS transport units with 

clamping system.  

It has to be used as given by the wagon holder. Intermediate wagons are 

not

 allowed. 

  Surfaces  of  bottom  and top  plastic  inlays  of  the clamping  rack  have to  be  cleaned  and 

degreased from lubricants before rails are loaded.  

  STS transport units are ideally loaded with fully allowed capacity in each layer. 

  Different from standard STS transport-units lubrication must be used and guaranteed on 

rail heads

 under every STS rack and each layer, 

as well as 15 cm to the right and left of 

this area.  

 

 

STS 40nn:

  

Mineraloil 

“TECTROL  TERRA  Chainsaw  oil“ 

or  similar  oil 

 

 

 

 

with same guaranteed characteristics. 

 

 

 

 

The use of grease is also permitted. (Type of grease see below)

 

 

 

STS 10nn: 

Fuchs  Plantogel  2  N 

or  similar  grease  with  same  guaranteed 

 

 

 

 

characteristics  

 

No lubrication on clamping system! 

 

ATTENTION:  Do  not grease  or  oil  all  STS  racks  and  rail  heads  on  the wagon  with  the 

clamping system. 

  Before using the clamping system, approx. 1 m in front of and behind the clamping system, 

the rail package has to tighten together with lashing straps in accordance with the 

UIC 

Loading Guidelines, Volume 2, Chapter 0.6 - Loading Information, Disposable Binder for 

Cargo Securing.

 

  No clamping on more than 

one wagon

 per rail package  

 

 

 

STS 40nn:

  

It is strictly forbidden to carry more than one rail package.  

 

 

 

 

Clamping on wagon No 3 by both installed clamping systems 

 

 

STS 10nn: 

60 m rails: 

 Clamping on Wagon No 3 (rail package no 1) 

and

 on 

 

 

 

 

wagon No 5 (rail package No 2) 

 

 

 

 

120 m rails: 

Clamping on Wagon No 3 by both installed  

 

 

 

 

Clamping systems 

 

 

 

The rail support arms and the clamping bar of none actively used clamping system 

must rest in the rest holders!

  

  Proper function and status must be checked before every train movement.   