IP DECT Deployment on Ships
A100K10676
Deployment Guideline for Outdoor Areas
8
The outdoor areas comprise:
main deck
-
terrace corridor one deck above the outer edges of the main deck
-
work areas at the outer edges of the main deck
-
hangar, i.e. the area of the ship where the ROV (Remotely
-
Operated Vehicle) is controlled and handled.
Hangar Deployment
8.1
Sync Master base station in Hangar on Main Deck
Figure 12
The Hangar can best be covered by using one standard base station; in
this deployment example, it is also the Sync Master (base station 1).
Main Deck Deployment
8.2
The Main Deck is not easy to cover, and we recommend using two base
stations – one in the cabin area of the ship in the fore section, and one in
the aft section of the ship – see figures below. One reserve PoE point is
installed at a strategic location in case of potential coverage holes.
ROV WORKSHOP
OFFLINE ROOM
ENGINE
CONTROL
ROOM
OFFICE
LAUNDRY
2
2
1/11
1
Sync Master
PLM-43
Cabinet
PoE
PLM-43
Cabinet