1) PRE-INSTALLATION CHECK LIST
1.1-
Check that all of the required components are
available. You should have 6 boxes. These are
colour coded so that identification of any handed
components is simple. The table below shows the
colour of the boxes that you require.
COMPONENT Left hand Right hand
Footplate box
Purple
Left
Green
Right
Purple Seat
Power pack
Blue
Fitting kit
Bottom track
section
Top track sec-
tion
e.g. a left hand lift comprises 2 purple and 4 blue
boxes; a right hand lift comprises 1 green, 4 blue and
1 purple boxes.
1.2- Installation tools required
- Toggle switch
- Short-circuiting switching connections
- 13mm Socket
- 17mm Socket
- 13mm Spanner
- 2.5mm Allen key
- 3mm Allen key
- 4mm Allen key
- 6mm Allen key
- 8mm Allen key
- No. 2 Pozi-drive
- Spirit level
- Small nose pliers
NOTE:
The installation engineer must check with Vi-
mec for the latest installation manual issue number.
2) TRACK ASSEMBLY
Items required:
- Fit kit
Splice bars x 3
Track ends cap x 1
Red bag
8 x bolts
4 x grub screws
Final limit switch x 1
Over-run microswitch x 1
- Top track section x 1
- Bottom track section x 1
- Three fixing support feet
Tools required:
- 6mm Allen key
- 3mm Allen key
- 2.5mm Allen key
- 13mm Spanner
2.1-
Position the bottom section of the track (2m)
on the stairs with the splice holes at the top
as shown in (Fig. 1). Regardless of the hand
of the lift the rack should always be on the
left hand side of the track when looking up
the stairs.
2.2-
Bolt in the splice bars to the bottom section
of track extrusion (Fig. 2) using 2 grub
screws for the top splice bar and the 4 bolts
in the bottom splice bars (from the red
fittings bag).