2.
Press key 6
E
whilst the progress
bar is filling from left to right.
The commissioning assistant starts.
Note
You can cancel the commissioning
assistant at any time using key
"Standard display"
F
.
The commissioning assistant can be
restarted (steps 1 and 2) by switching
ON/OFF switch
A
OFF and ON
again.
Drain
Press the following keys:
1.
y
/
x
for the required lan-
guage.
2. "OK"
to confirm;
"Safety
scan"
is displayed.
3. "YES"
to confirm;
"Access
rights"
is displayed.
4.
5243
as
"Code"
for the
"Contractor"
level.
5. "OK"
twice to confirm;
"Fault
messages"
or
"Pro-
gramming"
is shown.
6. "BACK"
if
"Fault messages"
is
displayed.
7.
To configure the system, e.g. select
the system scheme and available
components, see page 169.
8. "BACK"
for
"Sensor temps"
.
9.
y
/
x
for the required temper-
ature sensor (e.g.
"Outside"
,
"Evapora-
tor"
, etc.).
Note
Only temperatures for
correctly connected
sensors are displayed.
10.
0
/
=
to calibrate the selected
temperature sensor if
the displayed value dif-
fers from the actual
value by more than
1 K.
11. "BACK"
for
"Signal inputs"
.
12.
y
/
x
to check whether all
signal inputs are set to
"OFF"
.
Note
Check connection if
signal input is set to
"ON" (see page 215)
13. "BACK"
for
"Relay"
(outputs).
14.
y
/
x
for the required function
or connected compo-
nents (e.g.
"Compres-
sor"
,
"Central fault
mess."
, etc.).
Commissioning, inspection, maintenance
Further details regarding the individual steps
(cont.)
5414 828 GB
Service
Содержание VITOCAL 350-A
Страница 54: ...54 5 3x 7 6 3x 3x 3x Installation sequence Fitting the outer panels cont 5414 828 GB ...
Страница 57: ...57 3x 8 9 3x 3x 3x Installation sequence Fitting the outer panels cont 5414 828 GB Installation ...
Страница 58: ...58 2x 10 11 3x 3x Installation sequence Fitting the outer panels cont 5414 828 GB ...
Страница 60: ...60 4 mm 4x 4x 4x 3 2 1 2 2 Installation sequence Fitting the silencer hoods only type AWH O 5414 828 GB ...
Страница 62: ...62 Type AWH I 1 Installation sequence Installing the heat pump cont 5414 828 GB ...
Страница 63: ...63 Type AWH O 2 3 4 5 4x 1 Installation sequence Installing the heat pump cont 5414 828 GB Installation ...
Страница 115: ...115 Fitting the front panel 1 2 Installation sequence Closing the heat pump cont 5414 828 GB Installation ...
Страница 227: ...227 053 032 039 034 038 033 034 039 040 027 Parts lists Parts list type AWH I cont 5414 828 GB Service ...
Страница 228: ...228 052 054 059 008 056 025 020 Parts lists Parts list type AWH I cont 5414 828 GB ...
Страница 236: ...236 053 032 039 034 038 033 034 039 027 Parts lists Parts list type AWH O cont 5414 828 GB ...
Страница 237: ...237 052 054 059 008 055 025 020 Parts lists Parts list type AWH O cont 5414 828 GB Service ...