■ Expansion vessel must be
approved to DIN 4807. Dia-
phragms of expansion vessel and
safety valve must be suitable for
the heat transfer medium.
■ Discharge and drain pipes must
terminate in a container that can
hold the maximum possible expan-
sion volume of the heat transfer
medium.
2.
Ensure adequate thermal and anti-
vibration insulation of all pipes routed
through walls.
3.
Connect primary pipes to heat
pump.
!
Please note
To prevent damage to the
appliance, connect the pri-
mary lines to the heat pump
free of load and torque
stresses.
The primary lines must not
exert any pressure onto the
heat pump casing.
!
Please note
Ensure the hydraulic connec-
tions on the primary side are
tight in order to prevent the
formation of condensate
inside the heat pump.
■ With line entries, ensure the
diaphragm grommets on
the l.h. side panel are
seated correctly.
■ Make line entries air-tight.
4.
Insulate primary lines inside the
building with thermally insulating and
vapour diffusion-proof materials.
5.
Fill the primary circuit with
Viessmann heat transfer medium
and vent.
Installation sequence
Hydraulically connecting the primary/secondary…
(cont.)
5848 164 GB
Installation
Содержание BW 301.A090
Страница 44: ...44 A Frame screw Installation sequence Siting the heat pump cont 5848 164 GB...
Страница 157: ...157 5848 164 GB...
Страница 158: ...158 5848 164 GB...
Страница 159: ...159 5848 164 GB...