Victron energy Hub-4 Скачать руководство пользователя страница 3

2020-12-11 00:44

3/13

Hub-4 / grid parallel - manual DEPRECATED

Victron Energy - https://www.victronenergy.com/live/

Part no.

Description

REL100200000

Ziehl anti-islanding relay SPI1021 (Italy)

Grid sensor connection option A: wireless connection between the CCGX and the AC
sensor

ASS300400100

Zigbee to RS485 converter (AC Power adapter and 30cm wire to AC sensor is
included)

ASS300400200

Zigbee to USB converter (USB cable is included, connects to the CCGX)

Grid sensor connection option B: wired connection between the CCGX and the AC sensor
ASS030570018

RS485 to USB interface 1.8m

ASS030570050

RS485 to USB interface 5m

Notes:

The Multi or Quattro used needs to be a recent type with the new microprocessor (26xxxxx or

1.

27xxxxx). All units currently shipping have this new microprocessor. Also, the Multi or Quattro
needs to run the latest 4xx firmware. Contact your Victron representative for the firmware files.
Update instructions are 

here

.

The RS485 to USB interface cable from the CCGX to the AC sensor can be extended up to 100

2.

meters max.
The REL200100000 is the EM24DINAV93XISX from Carlo Gavazzi. Other EM24 models from

3.

Carlo Gavazzi can also be used, as the communication is the same. For example the
EM24DINAV53DISX, which uses Current Transformers and can therefore work in systems > 63A
per phase. Note that this model is not stocked by Victron Energy, we recommend to purchase it
locally.

2. Battery, inverter/charger and PV dimensioning

Battery size

There are several factors to take into account when dimensioning the battery:

Small batteries will be more cost effective: all available storage capacity is used every day
Small batteries will be charged and discharged with high currents: especially with lead batteries
this will reduce battery life time
Larger batteries, combined with a relatively large PV installation, can store excess power during
good days, which can then be used during several consecutive days of bad weather
Larger batteries provide longer autonomy during a power outage, requires using the UPS output

Inverter/charger size

Because it is installed parallel to the grid and the loads, the inverter size can be reduced to (much)
smaller than the max expected nominal and peak load.

For example, to cover the base load of a two person house hold, the MultiPlus xx/800 might already
be sufficient. For a household with one family, the MultiPlus xx/3000 can already manage nearly all
appliances, when not more than one of them is running at the same time. This means a MultiPlus
xx/3000 can already reduce the power consumption during late spring, summer days and early

Содержание Hub-4

Страница 1: ...gy is stored in the battery And that stored energy is then to power the loads at times when there is a shortage of PV power The system is managed by the Color Control GX CCGX which also provides exten...

Страница 2: ...bility is given to implement time shifting load management or other energy management optimization algorithms Either by ModbusTCP commands or by running additional self implemented code on the Color C...

Страница 3: ...ample the EM24DINAV53DISX which uses Current Transformers and can therefore work in systems 63A per phase Note that this model is not stocked by Victron Energy we recommend to purchase it locally 2 Ba...

Страница 4: ...nly one phase and compensate on that phase for the other two phases thereby e ectively regulating the total power of all three phases combined See the following example where the Hub is connected to L...

Страница 5: ...sate for the shortage Multis on phases with a net power production will be on idle Disabling phase compensation In a hub 4 system it is still possible to balance the grid power of each phase to 0W Dis...

Страница 6: ...ww victronenergy com live Printed on 2020 12 11 00 44 single phase setup diagram Note the jumper between terminals 1 and 4 Meter con guration Change the front selector of the AC sensor so it is not in...

Страница 7: ...USB converter to the CCGX using the supplied USB cable A few seconds after connecting the active LED should be on and the TX RX LED should be blinking the converter takes its power from the CCGX so th...

Страница 8: ...onverter Grid meter Yellow Terminal 41 Orange Terminal 42 Black Terminal 43 The Red Green and Brown wire are not used 5 Multi Quattro installation and con guration First follow the instructions as per...

Страница 9: ...entered as soon as the battery is discharged see above During Sustain Mode the batteries will slowly be charged from the grid maximum charge current is 5 Amp re The Sustain level is 12 5V for lithium...

Страница 10: ...he display will come to life If not check the wiring of the system 2 Within 60 seconds after power up the CCGX will detect the meter The meter will show up in 3 the device list on the display When sel...

Страница 11: ...sing terminals 3 6 and 9 Now you can chose on which phase you want the PV inverter by connecting the L1 line of the PV inverter to terminal 1 4 or 7 There are 3 options to connect the extra AC sensor...

Страница 12: ...sensor to measure both grid and PV inverter For wiring see the diagram below On the CCGX go to the grid meter in the Wired AC sensor settings Make sure Phase type is set to Single phase and PV invert...

Страница 13: ...n xxyy403 I get a lot of Low battery pre alarm warnings Solved by updating to xxyy403 or higher Does Hub 4 work for parallel systems Yes Hub 4 works for systems where multiple Multis or Quattros are i...