5.0 PERFORMANCE (CONTINUED)
Hydraulic Design
Single Slope Roof With Hip Calculation Procedure
Single Slope Roof Calculation - Dry System
1 Row Protection
• Calculate the 7 most hydraulically demanding contiguous DS sprinklers located along the high point plus the 2
most demanding sprinklers along the hip line. See Figure 24A.
• Minimum sprinkler flow is 20 gpm per sprinkler.
2 Row Protection
The following 2 sets of calculations shall be performed:
• Calculation #1: Calculate the 7 most hydraulically demanding contiguous DS sprinklers located along the high
point (peak) plus the 2 most demanding sprinklers along the hip line. See Figure 24B.
• Calculation #2: Calculate all sprinklers within the shaded corner Hip area as shown. See Figure 24C.
• Minimum sprinkler flow is 20 gpm per sprinkler.
Note: The "plus 2" most demanding sprinklers along the hip line may vary from that shown in the figures depending
on actual piping. Designer may need to investigate multiple options to determine the 2 most demanding sprinklers to
incorporate into the calculations.
FIGURE 24A: 1 ROW PROTECTION CALCULATION
FIGURE 24B: 2 ROW PROTECTION CALCULATION #1
FIGURE 24C: 2 ROW PROTECTION CALCULATION #2
FIGURE 24: SINGLE SLOPE DESIGN