20 Chapter 3 Installation
NetSure 801 AG1 Power Supply System User Manual
of the holes should be 35mm. To avoid being off-center, be careful not to shake the drill, and try to keep it as vertical
as possible to the floor.
Step 3: install expansive pipes
Clean the dust, and insert the expansive pipe into the reserve hole, knock it down gently using a hammer until the top
of the expansive pipe is level with the ground.
Step 4: place cabinet in position
Move the cabinet to the installation position aligning the installation holes of the cabinet with the reserve holes on the
ground.
Step 5: fix the cabinet
After the cabinet is in position, make some horizontal and vertical adjustments. Insert some iron pieces under the
lower edge and corner of the cabinet to adjust the vertical obliquity of the cabinet within 5 degrees. Finally, screw
down the bolt with plain washer into the drop in nut, and tighten it with wrench. The cabinet fixation is illustrated in
Tap bolt
Plain washer
Cabinet base
Ground
Spring washer
Expansive pipe
Figure 3-2 Fixing cabinet with bolt
3.2.2 Installation On Supporting Rack
If antistatic floor is laid in the equipment room, a supporting rack could be purchased from Vertiv.
Step 1: place cabinet in position
Install the supporting rack on the floor as shown in Figure 3-3. The installation steps are the same as the first three
3.2.1 Installation On The Floor
Expansive pipe finished
Floor
Expansive pipe
Bolt
Spring washer
Plain washer
Figure 3-3 Installing supporting rack