background image

 

 

Figure 2-16    Position of white terminal 

4. Plug the end of Temp. cable into the whitel terminal, and put the inserted 
terminal into the inside of the subrack, as shown in Figure 2-17.   

 

Figure 2-17    Connecting the terminal 

5. Fix the two screws of the cover plate, and attach the Temp. cable onto the battery pack, 
as shown in Figure 2-18. 

 

Figure 2-18    Fixing the screws 

For NetSure 2100 A31-S3 configuration, the corresponding controller is M831A, and a 
battery temperature compensation cable is configured. Take out the Temp. cable from the 
accessory at the site and connect the cable as above. When configuring one Temp. cable, 

one end of the Temp. cable is connected to the ‘Temp.1’ terminal, and the other end is 

attached to the battery pack. When configuring two Temp. cables, connect one end of the 

Temp. cables to the ‘Temp1’ and ‘Temp2’ terminals respectively. The other end of Temp1 

is attached to the battery pack, and the other end of Temp2 cable is pasted in the 
corresponding position according to actual order requirements. 

2.5    Installation Check   

After the installation, you should carry out the inspection procedures given in Table   2-3. 

Table 2-3    Installation check list 

No. 

Check content 

Check that the power system is horizontally, vertically and steadily fixed 

Check that all the bolts are tightened, especially those in electrical 

connections. Check that the bolts have plain washers and spring washers and 

are not reversed 

Check that there are no unwanted materials inside the cabinet and clear up 

the unwanted materials 

Check that the power system is intact. If there are scratches, paint them 

immediately with antirust paint to prevent corrosion 

Check the correctness of all MCBs and cables specifications 

Check the correctness of input and output cable connection, and 

communication between the power system and the system grounding. Make 

sure that all the cable connections are firm and reliable and the cable binding 

is tidy and normative 

Check the correctness of the battery strings polarities 

Measure the resistance value between the positive terminal and negative 

terminal and phase- to - phase resistance value in the AC loop. Make sure that 

there is no short-circuit 

Check the AC input and distribution. Check that the color of the AC cables is 

normative, the cables are laid stably, and the safety labels are complete 

10 

Check that the rectifiers are clipped tightly 

11 

Check that all the MCBs are switched off 

 

3    Testing 

During testing, the corresponding safety regulations must be observed, and the testing 

procedures should be followed strictly. The system has been tested before delivery, the 

user does not need to carry on the field testing. 

3.1    Testing Distribution Unit And Rectifiers 

 

Note   

Before the test, inform the chief manufacturer representative. Only trained electrical 
engineer can maintain and operate this equipment. In operation, the installation 
personnel are not allowed to wear conductive objects such as watches, bracelets, bangles 
and rings. 

 

During operation, parts of this equipment carry hazardous voltage. Wrong operation may 
result in severe or fatal injuries and property damage. Before the test, Installation check 
must be done before testing. Then the batteries can be charged for the first time. 

Make sure that the upstream AC output MCBs and load MCBs inside the subrack are 
switched off. Make sure that all the devices are properly installed. 

Please check the power system according to below listed items. 

Startup preparations 

Check item 

OK 

Remark 

Make sure that all the MCBs are switched off. 

 

 

Measure the AC input voltage. Make sure the input voltage is 

within the allowable range. 

 

Umin=    V 

Make sure that the communication and dry contact alarm output 

cable are connected to the monitoring board 

 

 

Make sure that the temperature sensor is installed correctly 

 

 

Use a voltmeter to measure the battery string voltage and make 

sure the battery polarities are correct 

 

Umin=    V 

Check with an ohmmeter that there is no short circuit between 

the positive & negative terminal of DC output, between the 

positive & negative battery poles or AC input terminals (Note: 

Pull out all modules before the check and restore them after the 

check) 

 

 

 

Startup 

Check item

 

OK 

Remark 

Switch  on  the  system  AC  output  MCB,  the  green  LED  on  the 

rectifier will be on after a certain delay 

 

 

Switch on  the load MCB.  Use a multimeter to check the voltage 

of  both  ends  of  load,  if  it  shows  53.5V  ±  0.5V,  the  voltage  is 

normal 

 

 

Switch on the battery MCB 

 

 

 

3.2    Basic Settings 

The parameters of the power system are set at the factory, and the factory default setting 
can meet the normal use of the power system. Users can modify the parameters (like AC 
over/under-voltage point, DC over/under-voltage point and so on) of the power system 
through background software. Users can also reset the commonly used parameters based 
on actual needs through LCD screen of the controller. When setting the system 
parameters, the user must enter the correct password before setting the parameters for 
the controller. For NetSure 2100 A31-S2 configuration, the password of M225S controller 
is 1. 

The parameters that users can check and set are listed in Table 3-1. 

Table 3-1    Settable parameters of power system 

Parameter 

Setting range 

Default 

setting 

Battery capacity 

20Ah ~ 600Ah 

100Ah 

Battery protection 

40V ~ 60V 

43.2V 

Float voltage 

42V ~ 58V (lower than boost voltage) 

53.5V 

Boost voltage 

42V ~ 58V (higher than float voltage) 

56.4V 

Shunt current 

1 ~ 500A 

75A 

Shunt voltage 

1 ~ 150mV 

25mV 

ECO enable 

Enable/disable 

Disable 

Rely2 

Load disconnect or alarm output 

Alarm output 

Walk in Time 

1 ~ 128s 

0s 

Note: 

1. The battery protection voltage should be set according to battery manufacturer 

requirement. 

2. If iron lithium battery is configured by user, set relevant charging parameters 

according to the requirements of the battery manufacturers 

Содержание NetSure 2100 A31-S2

Страница 1: ...drop mechanical strength and the cable design should meet relevant industry standards With cable length shorter than 30m the CSA calculation should be based on the current density of 2 5A mm2 The suggested CSA value is not more than 10mm2 Select the DC load cable CSA according to the Table 2 1 Table 2 1 DC load cable CSA selection Load route rated current Max output current Min cable CSA Max cable...

Страница 2: ... 3 MCB Load output route 4 MCB Load output route 4 MCB Load output route 3 MCB Load output route 2 MCB Load output route 1 MCB Battery input terminal Temp cable input port Figure 2 7 NetSure 2100 A31 S3 layout 2 4 1 Connecting Earth Cable A M6 grounding stud is reserved on the mounting bracket The grounding cable is yellow green double color cable with cable specification up to 10mm2 The cable end...

Страница 3: ...nd then insert the terminal into the controller front panel as shown in Figure 2 11 Users need to prepare signal cable themselves Table 2 2 Correlation of ports RS232 port DB9 port 1 Tx 2 2 Rx 3 3 GND 5 Connecting M831A dry contact output port The controller is configured with four pairs of alarm dry contact output DO1 DO4 as standard configuration and two routes of DI input and one route of RS485...

Страница 4: ...cal engineer can maintain and operate this equipment In operation the installation personnel are not allowed to wear conductive objects such as watches bracelets bangles and rings During operation parts of this equipment carry hazardous voltage Wrong operation may result in severe or fatal injuries and property damage Before the test Installation check must be done before testing Then the batterie...

Страница 5: ...Charge Shunt Number 1 String1 norminal capactity Batt Charge String1 norminal capactity 100Ah String1 rated current Batt Charge String1 rated current 75A String1 rated voltage Batt Charge String1 rated voltage 25mV Float voltage Batt Charge Float voltage 53 5V Boost voltage Batt Charge Boost voltage 56 4V LVD2 Enable LVD LVD2 Enable Enable LVD2 voltage LVD LVD2 voltage 43 2V Contactor type LVD Con...

Отзывы: