10 CHECKLIST FOR COMPLETED INSTALLATION
10.1 Moving and Placing Equipment
1. Unpack and check received material.
2. Proper clearance for service access has been maintained around the equipment.
3. Equipment is level and mounting fasteners are tight.
10.2 Electrical Installation Checks
1. Supply voltage and phase matches equipment nameplate.
2. Power wiring connections completed to the disconnect switch, evaporator unit and heat
rejection equipment.
3. Power line circuit breakers or fuses have proper ratings for equipment installed.
4. Control wiring connections completed between indoor evaporator and heat-rejection
equipment.
5. All internal and external high- and low-voltage wiring connections are tight.
6. Confirm that unit is properly grounded to an earth ground.
7. Control transformer setting matches incoming power.
8. Electrical service conforms to national and local codes.
9. Check blowers and compressors for proper rotation.
10.3 Piping Installation Checks
1. Piping completed to refrigerant loop.
2. Piping has been leak-checked.
3. Additional oil has been added for system charges over 40 pounds (18.1kg) per circuit. See
Additional Oil Requirements for Scroll and Digital-scroll Compressors
4. Piping is properly sized, sloped and trapped as shown in the piping schematics.
5. Check piping inside and outside of equipment for proper support and adequate spacing to
prevent rub-through.
6. Ensure that factory clamps have been reinstalled.
7. Drain line connected, not obstructed, and pitched per local code.
10.4 Other Installation Checks
1. Ducting or plenum assembly complete (if required), maintain access to filters.
2. Filters installed.
3. Check fasteners that secure motors—some may have become loose during shipment.
4. Verify water detection is properly installed around all units (recommended).
5. Blower drive system rotates freely.
6. All fans are free of debris.
7. Set fan air-flow calibration voltage. Refer to Table 3.4 on page 18, for values. The values are
set in the iCOM Service menu >
Setpoints
>
Fan
.
10 Checklist for Completed Installation
49
Содержание Liebert DSE
Страница 10: ...Vertiv Liebert DSE System Design and User Guide 10 This page intentionally left blank ...
Страница 15: ...Figure 2 2 Downflow bottom discharge blower configurations with EC fans 2 Nomenclature and Components 15 ...
Страница 16: ...Vertiv Liebert DSE System Design and User Guide 16 This page intentionally left blank ...
Страница 20: ...Vertiv Liebert DSE System Design and User Guide 20 This page intentionally left blank ...
Страница 22: ...Vertiv Liebert DSE System Design and User Guide 22 This page intentionally left blank ...
Страница 24: ...Vertiv Liebert DSE System Design and User Guide 24 This page intentionally left blank ...
Страница 32: ...Vertiv Liebert DSE System Design and User Guide 32 This page intentionally left blank ...
Страница 36: ...Vertiv Liebert DSE System Design and User Guide 36 This page intentionally left blank ...
Страница 46: ...Vertiv Liebert DSE System Design and User Guide 46 This page intentionally left blank ...
Страница 50: ...Vertiv Liebert DSE System Design and User Guide 50 This page intentionally left blank ...
Страница 52: ...Vertiv Liebert DSE System Design and User Guide 52 This page intentionally left blank ...
Страница 66: ...Vertiv Liebert DSE System Design and User Guide 66 This page intentionally left blank ...
Страница 68: ...Vertiv Liebert DSE System Design and User Guide 68 This page intentionally left blank ...
Страница 98: ...Appendix C Guide Specifications The following are the guide specifications for the Liebert DSE 69 ...
Страница 99: ...Vertiv Liebert DSE System Design and User Guide 70 This page intentionally left blank ...
Страница 119: ...Vertiv Liebert DSE System Design and User Guide ...