38 Chapter 4 Commissioning Instructions
SmartCabinet Series Solution Product for IDC or Computer Rooms User Manual
Note
1. For the cautions in the UPS startup process, refer to the Liebert
®
ITA 3kVA UPS User Manual and Liebert
®
ITA2 5kVA
~
20kVA UPS User Manual.
2. The PMU contains a SPD module, so ensure that the PMU SPD MCB is closed when the SmartCabinet is powered on for
operation.
3. Prior to the startup of the SmartCabinet, ensure that the maintenance bypass switch is opened and is locked by a sheet metal
lock.
4. If an intelligent lock is selected, prior to using the intelligent lock, confirm the configured access control card can normally
open the intelligent lock.
Warning
The startup of SmartCabinet system should be completed by authorized professional technician, and we recommend the
personnel from Vertiv service center shall do this work.
Figure 4-3 Layout of MCBs
4.5 System Commissioning
Figure 4-4 SmartCabinet LCD screen
1. Upon SmartCabinet startup, the default screen is displayed by the LCD as shown in 1st Figure of Figure 4-4.
2
. In LCD local display screen, click “Setting”->”Configuration”, and the display screen configures the selection
screen, and user can select the corresponding configuration option according to the equipment connection condition,
as shown in 2rd Figure of Figure 4-4.
3. In the countdown process, the SmartCabinet system will restart to upgrade the configuration, and after the
configuration upgrading is successful, the LCD interface will automatically jump to the system main page.
4. You can check whether the equipment enter the normal operation status via LCD.
5. After all the equipment run normally, you can start user server and other IT devices.
总输入
Main Input
防雷器
SPD
UPS 输入
UPS Input
维护旁路
Maitenance
Bypass
空调
AC
UPS 输出
UPS Output
PDU1
PDU2
预留
Future
Extensiont
直流输出
DC Output
非专业人士请勿操作
TO BE OPERATED BY
AUTHORIZED
TECHNICAL PERSON
ONLY