Always connect the EZCT-2000 to the substation ground before connecting any test cables. The
EZCT-2000 is supplied with five 20-foot X test cables and one 35-foot H cable. The X cable
connections are required to run the current transformer excitation test. The H and X cable
connections are required to run the transformer turns-ratio test. A typical excitation and ratio
test connection is shown in Figure 2. Transformer bushing CT connections for Delta and Y
transformers are shown in Figure 3 and Figure 4, respectively.
Figure 2. Typical EZCT-2000 Excitation and Ratio Test Cable Connection
Содержание EZCT-2000
Страница 25: ...REV 3 EZCT 2000 USER S MANUAL 21 Figure 6 Typical EZCT 2000 Tabulated Report Printout ...
Страница 33: ...REV 3 EZCT 2000 USER S MANUAL 29 Figure 9 Typical Internal Test Record Directory Printout ...
Страница 39: ...REV 3 EZCT 2000 USER S MANUAL 35 Figure 10 Typical EZCT 2000 Flash EEPROM Test Plan Directory Printout ...