Storage
• Storage area should be clean, dry, dark and free of mechanical
and environmental damage.
• Storage temperature should be no more than +70 degrees Celsius
(158°F) for short term storage (less than one week) and no more
than +30 degrees Celsius (86°F) for long term storage.
Inspection and Removal from Service Criteria
Inspect individual Chain Links thoroughly before each use for
abrasion, tears, cuts or other damage which might affect the
performance of Green Pin Tycan
®
Lifting Chain.
The pictures show defined areas of
Green Pin Tycan
®
Chain Link, such
as the Link Leg and Interface. Which
allows for different amounts of wear
and tear:
• Zero tolerance for damage allowed
in Link Bearing Point.
• No folding or spreading out of
layers allowed in Link Bearing
Point.
Connecting Green Pin Tycan
®
Lifting Chain directly into hooks
(components) where the width/clevis is more than required minimum
clevis width is not acceptable. Doing so can cause the layers to
spread apart, which in the utmost consequence could have a negative
effect on the strength of the chain. The only exception is when it
is not an open end-link and both load bearing-points of the link is
under tension from the adjacent chain links. An example of this is the
anchored basket hitch showed in this manual.
Shortening Green Pin Tycan
®
Lifting Chain
Shortening Green Pin Tycan
®
Lifting Chain can be attained by using:
• Green Pin Tycan
®
Grab Hook CL GR10 - GPUCRCT15; WLL 2.6t
• Green Pin Tycan
®
Grab Hook CL GR10 - GPUCRCT20; WLL 4t
• Green Pin Tycan
®
Grab Hook CL GR10 - GPUCRCT25; WLL 5t
• Green Pin Tycan
®
Grab Hook CL GR10 - GPUCRCT30; WLL 6.8t
The Green Pin Tycan
®
Grab Hook CL GR10 must be assembled with
(at least 5) links of chain to the master link with a connecting link
(UMJ(T)). Do not connect two Green Pin Tycan
®
Lifting Chain ends
into one connecting link (UMJ(T)).
The unloaded link must never be placed between the loaded link
and the body hook.
Interface
Link Leg
Link
Bearing
Point