Produced in accordance with Article 3, paragraph 3 of the PED - European Pressure Equipment Directive - 97/23/EC 

IMI 1.3960 E 04.14 

 
START UP 
 

 

 

 

Current regional safety regulations should be take in to account and followed. 

Protective insulation and warning notice may be required. 

Until the start up of an existing or a new plant, the following must be checked: 

 All works are completed. 

The steam trap is correctly installed. 

All the necessary safety devices have been installed. 

At start up, the presence of small particles in the fluid (dirt, scale, weld splatters, joint particles, remains 
of Teflon  tape,  etc)  may  cause  an  imperfect  closure  of  the  seat.  If  this  occurs,  proceed  to  an  accurate 
cleaning.  

 
 
 
 

Periodical checking:   
 

 

24 hours after the start up, it is recommended to check pipe connections for leaks and retighten the connections 
if necessary. 

 

 
 
 

MAINTENANCE 
 

 

We recommend the steam traps to be serviced as necessary.  Steam traps should be checked periodically  (at 
least yearly), to verify if they are operating correctly and to clean the internal parts and strainer screen (if any). 

 

When  reassembling  make  sure  that  all  gasket  faces  are  clean  and  always  use  a  new  gasket.  Tighten  cover 
bolts uniformly in a diagonal sequence. 

 

Maintenance should proceed as follows: 

 
1.  Isolation valves should be closed and the pressure and temperature must be atmospheric. 
2.  Remove the type of connections used. 
3.  Execute the maintenance work. 
4.  Replace and tighten the connections. (Don’t forget to substitute the gasket). 
5.  Consider the start up conditions. 
 

 

TROUBLESHOOTING 

 

 

 

 

If the malfunctions cannot be solved with the help of the following chart, please consult the manufacturer. 

Some of these faults may only occur in some models.  

 
 
 
 
 

Содержание FLT14I Series

Страница 1: ...t be carried out by trained personnel A supervisor must follow and check all activities For the problems that cannot be solve with the help of this instructions please contact the supplier or the manu...

Страница 2: ...advised to assess the risks taking into account the task the individual the load and the working environment Before starting work ensure that you have suitable tools and or consumables available Use...

Страница 3: ...p maintenance The by pass must be kept close during the normal operation Procedure Prior to install check that the product is suitable for the intended application materials and pressure temperature r...

Страница 4: ...up it is recommended to check pipe connections for leaks and retighten the connections if necessary MAINTENANCE We recommend the steam traps to be serviced as necessary Steam traps should be checked...

Страница 5: ...reason of contamination Check the steam trap D P and substitute Replace the steam trap by a superior DN or use ADCAMAT Replace Temporary condensate accumulation Steam blocking Downsizing Use a steam...

Страница 6: ...ARTS Available spare parts POS Nr DESIGNATION M ATERIAL 1 Body CF8M 1 4408 2 Cover CF8M 1 4408 3 Gasket Stainless st Graphite 4 Seat AISI 410 1 4006 5 Valve AISI 440C 1 4125 6 Lever AISI 304 1 4301 7...

Страница 7: ...of contaminating fluids and residues or mechanical damage that may represent a health safety or environmental risk must be provided in writing by the distributors and costumers when returning products...

Отзывы: