background image

Page 13 of 14 

GEN2-V1 10-ft Instructions (Generic) doc:r1 

16. TIGHTEN THE FABRIC:

 

 
Locate the Manual Crank handle and hook it into the loop on the gear mechanism, turn counter clockwise to roll the 
fabric around the Roller tube and remove any slack in the fabric.  

YOU MAY NOW CUT THE PLASTIC ZIP TIES ON EACH OF THE EXTENSION ARMS, THEY SHOULD 
IMMEDIATELY PUSH OUTWARD AND TAKE ANY ADDITONAL SLACK OUT OF THE FABRIC. 

 

 
17. INSTALL SPLINE STOPS & VALANCE TUBE END CAPS  

We recommend that you go through the Adjustment and Fine Tuning of your 
Awning before completing step 17, however when complete, finish your 
installation as follows: 
 

 

Cut any e

xcess SPLINE an additional ½” (12.7mm), on both ends 

of the ROLLER TUBE and VALANCE TUBE such that the SPLINE 
STOPS can be installed in the end of each channel, then tighten 
the phillips head screw to secure in place.  

 

Slide the Right and Left Side VALANCE TUBE END CAPS over 
each end of the VALANCE TUBE. 

 

18. ADJUSTMENT & FINE TUNING OF THE AWNING: 

Every Awning will require minor adjustment to operate correctly. The 
following section will walk you through the minor adjustments required to 
make you awning operate correctly:

 

 

 
Pitch Adjustment:  

If the pitch is set much different on each end it will be difficult to make other 
adjustments. Ensure that the EXTENSION ARM PIVOT Bracket is mounted 
in the same hole on the LEFT and RIGHT Side Brackets. Pivot adjustment 
can be achieved by loosing the EXTENSION ARM PIVOT BRACKET 
BOLTS, and then using the PITCH ADJUSTMENT BOLT screw you can 
position the awning pitch equally on the right and left sides. Once you’ve 
reach your pitch preference, you must retighten the EXTENSION ARM 
PIVOT BRACKET BOLTS.

 

 
 
Fabric Roll: 

The following is the most common adjustment and will be necessary to ensure the awning opens and closes properly 
as well as ensuring the fabric rolls around the roller tube evenly. Insert your Crank Handle in the Gear Mechanism 
Loop; turn counter clockwise the fabric will release and the awning will roll out. Once you get the fabric out, roll it back 
in. You want to be watching for the following: 

 

The RIGHT and LEFT Extension arms are operating equally, in other words the elbow (or centre joint) in 
each Extension arm should be opening and closing equally. 

 
The image below, shows an awning opening only about half way; notice how the awning arms are positioned in 
relation to each other. You want the Extension Arms opening and closing as close to evenly as possible as shown in 
the diagram below. 
 
 
 
 
 

EXTENSION ARM 
PIVOT BRACKET 
BOLTS 

PITCH 

ADJUSTMENT 

BOLT 

IN-CORRECT 

CORRECT 

Содержание APR-100810 Series

Страница 1: ...ning section for all assembly and installation instructions set up adjustment and troubleshooting instructions There you will be able to see common problems and how to rectify them usually with a simp...

Страница 2: ...carbide masonry drill bit This will essentially use the header board to provide the level surface for the awning but will use the greater strength of the masonry wall for holding power You may contac...

Страница 3: ...ETRACTABLE AWNING SCHEMATIC DRAWING Size 8 ft Projection X 10 ft Width Diagram Exploded View 12 LEFT BRACKET ASSEMBLY 13 RIGHT BRACKET ASSEMBLY GEAR MECH ROLLER TUBE SUPPORT BRACKET ROLLER TUBE SUPPOR...

Страница 4: ...mbly 1 14 40x40x240mm Torsion Bar w plastic end caps 1 15 Wall Brackets w hardware 2 16 Extension Arm Shoulder Bracket w hardware 1 17 Extension Arm Pivot Mount w hardware 1 18 Wrist Pin Assembly w ha...

Страница 5: ...determine the location of the awning Go to Additional Material Hardware Requirements above for fastening options Non Masonry Surface Installation As the awning is quite heavy and the forces put on th...

Страница 6: ...m of 1 1 2 to 2 38 51mm of unobstructed clearance above this point 9 MOUNTING A HEADER BOARD The Awning Height reference is the upper most point of the Awning Fabric after installed The mounting brack...

Страница 7: ...rk this point on the center plumb line already marked Measure the 51 7in 1313mm from the horizontal centre line to the right a mark this point on the plumb line Header Board Vertical Centre Plumb Line...

Страница 8: ...nted to it from the LEFT WALL BRACKET ASSEMBLY 3 Remove the three Allen bolts that are securing the GEAR MECAHNISM TO the support bracket and move it to the opposite side of the ROLLER SUPPORT BRACKET...

Страница 9: ...e Vertical Centre Plumb Line Set the Intersection point labeled L over the Vertical Line and the Plumb line Align Plumb Line marked on the Wall or Header the Plumb Line on the Template Mark the Centre...

Страница 10: ...llapse and re insert in the hole Using a 5 8 wrench or adjustable wrench tighten each bolt until snug DO NOT OVERTIGHTEN THESE BOLTS On masonry if you find that each bracket is not laying flush on the...

Страница 11: ...r tube carefully slide the fabric into the channel be sure not to damage the fabric on the ends of the aluminum tube ends Centre the fabric on the Roller tube the fabric should be approximately 5cm sh...

Страница 12: ...n Arms Carefully open the box and find the LEFT and the RIGHT Extension Arm Each arm is Labeled LEFT and RIGHT and each or them indicates TOP meaning that top should face upwards when installing the p...

Страница 13: ...tch is set much different on each end it will be difficult to make other adjustments Ensure that the EXTENSION ARM PIVOT Bracket is mounted in the same hole on the LEFT and RIGHT Side Brackets Pivot a...

Страница 14: ...er direction as required within the channel on the bottom of the Valance Tube Be careful to ensure that you maintain even alignment of the end of the Valance Tube and the Roller Tube while making this...

Отзывы: