11. FULL OPERATING CHECKS
•
When operating the fire for the first time, some vapours may be given off which
could set off smoke alarms in the vicinity. These vapours are quite normal with new
appliances. They are totally harmless and will disappear after a few hours use.
•
This fire may be controlled manually, by use of the controls mounted on the
appliance. The flame settings may also be controlled by means of the remote control
handset
11.1
Preliminaries
1.
Remove the elastic band retaining the
remote control receiver.
2.
Slide the remote control receiver out of its
retention housing. Remove the receiver top
cover and fit the four AA batteries as
indicated inside the receiver base.
Replace the receiver top cover. Slide the
receiver back into its housing.
The ultra-
sonic sensor must face towards the centre
of the appliance and the supply cable must
be routed as shown in figure 19.
3.
Fit the PP3 battery to in the remote control handset.
4.
Open the isolating valve on the inlet connector.
11.2
Aeration control
system
This appliance is fitted
with an aeration control
(See figure 20). Its
operation should be
noted and set as required
when carrying out the
operating checks and
generally operating the
appliance.
To operate the aeration
control system, the
following procedure
should be followed:
•
Allow the appliance to warm up, (for at least fifteen minutes) in the fully aerated
position, with the aeration control lever pushed in to the locked position (See figure 20,
&
6
in figure 21).
Figure 19 Remote control receiver