16
VADA FLOW BOSS
JET PUMP
VFB-J60
INSTALLATION MANUAL
INSTALLATION
PART 3: DISCHARGE
SET UP
Now that your suction pipework is installed,
it’s time to set up the discharge pipework.
1. Select a pipe with an internal diameter
of 25mm or larger (this is the size of the
discharge outlet port).
2. Connect the pipe to the Jet Pump using
a 25mm barrel union.
Note:
It is crucial that you use the
recommended pipe size until at least the first
pipe branch (T piece) is reached.
25mm
Isolation
valve
25mm Y Strainer
25mm Barrel union
10
0m
m
PART 4: PUMP PRIMING
Before moving on, its important to prime the
pump. This means filling the pump with water
and expelling all air from within the pump
casing.
If you’ve set up a surface mount pump, follow
steps outlined in Part 4A.
If you’ve set up a pump mounted above a tank,
follow steps outlined in Part 4B.
PART 4A: PRIMING A
SURFACE MOUNT PUMP
AND TANK
1. Ensure the water level in your tank sits
above the tank outlet. This will ensure
the pump does not draw in any air during
priming.
2. Open the isolation valve on the tank. If there
are any leaks, repair these immediately.
If no leaks are present, proceed.
OPEN