6
Fold Down Guardrails
This procedure is only for passing through door-
ways. Guardrails must be returned to proper
position before using the machine.
Fold Down Procedure (Figure 6)
Note: When performing the following proce-
dures retain all fasteners.
1. Place controller on platform.
2. Starting at the front of the platform, remove
nuts, bolts and washers from the top of the
front guardrail. Fold the front guardrail down
onto the platform.
3. Close and latch the gate.
4. Remove nuts, bolts and washers from the top
of the rear guardrail. Fold the rear guardrail
down onto the platform being careful to keep
gate latched at all times.
5. Remove nuts, bolts and washers from the top
of the side guardrails and from the slideout
deck midrail. Lift up and fold one side guard-
rail in so it rests on the deck. Repeat with other
side guardrails.
Figure 6: Fold Down Guardrails
Erection Procedure
IMPORTANT: After guardrails have been com-
pletely assembled, torque all hardware to values
specified in torque chart on page 10.
1. Raise side guardrails making sure each is
pushed down to secure the guardrail in the
vertical position.
2. Install bolts, washers and nuts between the side
guardrails.
3. Raise rear guardrail assembly, aligning holes
and install bolts, washers and nuts.
4. Raise front guardrail, aligning holes and install
bolts, washers and nuts.
5. Hang controller on front guardrail.
6. Before operating work platform check that all
fasteners are in place and properly torqued.
Before operating machine, guardrails must be
securely fastened in their proper position.
Double Deck Fold Down Procedure
(Figure 7)
NOTE: When performing the following proce-
dures retain all fasteners.
1. Place controller on platform.
2. Starting at the front ; slide out deck, remove
hardware from top front corners of guardrails.
Remove hardware from the slide out deck side
guardrail midrails. Also remove hardware from
the top of the sockets that hold the slide out
deck side guardrails to the deck. Fold the side
guardrails down onto the platform.
3. Follow step 2 to fold the front side guardrails
on the rear slide out deck.
4. Unlatch the gate so the left side guardrails can
be folded down in two separate pieces. Also
remove the hardware opposite the gate latch on
the right side guardrail so it can be separated
into two pieces.
5. Lift up and fold side guardrails in so they rest
on the deck.
6. Lift up and fold front guardrail in so it rests on
the deck. Repeat for rear guardrail.