INSTALLATION GUIDE
PAGE
HIGH DENSITY 5-DEGREE
BALLAST RACKING SYSTEM
9
Step 3 – Secure PV Modules onto Bases
• Place PV module onto EcoFoot5D Base.
• Space modules ½” apart using alignment marks located on the Clamps.
Torque Nuts to 14 ft-lbs using a 1/2" deep socket.
Step 4 – Install Mid-Support
Locate module center point +/-1”
using PV module cell lines.
Slide the Upper and Lower Mid-Support
slots onto module frame.
Press Upper down to sit fl at on the
roof.
Press Lower down and snap onto
tongue of upper.
Installation Tips
• After Step 3, wiring can be routed and secured.
• Standard wire clips or cable ties (not included) can be inserted into slots
along Base edge
Nut
Module
Base
Nut
Upper & Lower
Mid-Support
Note: Mid Support kits are used between rows and on the North and South array edges where ballast trays will be installed.
PV Module
Center Point
SYSTEM INSTALLATION STEPS