3: Installation
30
TS_604_01 PowerWave PW3000/TP User Manual UK 5/1/18
3.7.2 Three phase dual input cabling details
Figure 3.8 Three phase dual input diagram with recommended cable and fuse sizing
MAINS DISTRIBUTION BOARD
Ext. BATT CAB
UPS CABINET
RECTIFIER
INVERTER
STATIC SWITCH
LOAD DISTRIBUTION BOARD
L1
L2
L3
N
GND
M2
N
L1
L2
L3
N
GND
GND
GND
GND
GND
M2
N
L
N
GND
L
N
GND
JP1 JP2
GND
B+
B-
GND
B+
B-
Fu
se
B
Ca
bl
e
B
Fu
se
A
Ca
b
le
A
Ca
b
le
C
Cable D
Fuse D
UPS Mains Supply
(3 x 380/400/415V)
UPS Bypass Supply
(1 x 220/230/240V)
WIRING NOTES
1. Connect the supply neutral to the bypass neutral
terminal (Mains 2 (N)).
DO NOT connect the supply neutral to the input
neutral terminal (Mains 1 (N)) as there is a
possibility that the bypass current could return
through, and overload, the smaller cable of Mains
1.
2. Connect the three-phase mains input cable to
L1,L2,L3 and the bypass input cable to M2.
3. Connect the battery cables to the external battery
cabinet if used (see paragraph 3.8).
4. Remove the link between JP1 and JP2 if the
module is part of a parallel module system.
5. Connect the output terminals to the output
breaker/load distribution board. The load
distribution breakers should have a leakage
current protective function to suit to the UPS
voltage and current ratings.
10kVA
20kVA
Cable A
16 A
33 A
Cable B
48 A
90 A
Cable C
48 A
90 A
Cable D
Bespoke
Safety Earth
max 16 mm
2
max 25 mm
2
Note: @400V/230V nominal input.
L1
L2
N
M2
GND
L3
GND
N
L
N
JP1
GND
JP2 B+
GND
B-
MAINS 1
(Input)
MAINS 2
(Bypass)
OUTPUT
PARALLEL
JP
BATTERY
Internal link