Diagram 8 

7.  If you have not yet done so, remove the front cover 

(complete with control knob) of the unit by undoing 
the retaining screws at the top and bottom of the unit 
and lifting the cover off. The top-fixing hole is a 
keyhole slot, and should be marked and drilled first. 
Tighten top screw with head protruding about 10mm 
from wall and hook the back-plate over the screw 
head. This allows for correct and accurate alignment 
of your shower before marking and fixing the 
bottom/side position. You may not wish to tighten up 
all 3 screws at this stage as the holes are elongated 
to allow for adjustment after other connections have 
taken place. 

 
WARNING! TAKE CARE NOT TO DAMAGE THE 
PRINTED CIRCUIT BOARD IN ANY WAY.         
DURING INSTALLATION AVOID DUST AND DEBRIS 
GETTING ON IT. 
 

8.  Do not obstruct the pressure relief device found in 

the back-plate slot underneath the outlet connection 
(see diagram 3). Especially if silicone sealant or 
similar materials are used around the edges of the 
back-plate. 

 
9.  There are a number of clearly marked shields in the 

shower unit. These are important for the correct 
operation of this shower and MUST NOT be removed under any circumstances. 

 

b) Plumbing (see diagram 9) 

 
The heater should be connected to the mains cold water supply. 
This must have a minimum running pressure of 100kPa (1.0 bar, 4.5 p.s.i) and a maximum 
pressure of 1000kPa (10 bar, 145 p.s.i). 
Before connecting the pipe-work to the shower ensure that pipe-work is flushed out. 

 

1.  It is recommended that a WRAS (Water Regulations Advisory Scheme) listed isolating 

valve is fitted between the rising main and the unit. This will allow the unit to be serviced 
without turning off the cold water or exchanged without having to turn off the water at the 
water mains stop valve. 

 

2.  The heater can be fed from a header tank provided this has a minimum head height of 

10.5 metres (35ft). 

 
 

3.  Ø15mm copper or stainless steel pipe should be used with a standard compression 

fitting. In multiple shower installations correct pipe-work sizes should be calculated to 
maintain adequate flow to each shower. 

 

4.  a) If top entry is chosen, turn the elbow 180

°

 into the required position and fit a standard 

15mm in line compression fitting.                                                                                                 
There is a removable side section, which will aid you with this (diagram.7). 
b) If rear entry is chosen, turn the elbow 180

°

 and treat it as top entry except for the fitting 

of a ‘Yorkshire’ elbow in the rear channel.                                                                                          
The removable side section will again be an aid. 
 

5.  It is permissible to use a WRAS (Water Regulations Advisory Scheme) approved sealant 

sparingly whilst avoiding excess finding its way into shower operating parts. 

Diagram 7 

Содержание AX310

Страница 1: ...Shower Handbook IMPORTANT Please retain this booklet for future reference We offer a technical advisory service on the telephone to contractors and other customers with problems in the field RING 084...

Страница 2: ...ng push button D only The electricity to the elements is then disconnected and the adjacent light will flash water will continue to flow for approximately 5 seconds before switching off This reduces t...

Страница 3: ...t have a serial number How your shower works Your shower is designed for convenience economy and safety of use 1 Water is heated instantaneously as it flows over the heating elements in the copper hea...

Страница 4: ...of pressure occur within the shower 9 There are a number of defined spray plate settings modes patterns adjustable by rotating the spray plate see diagram 4 The modes patterns have a positive click to...

Страница 5: ...wing water off Raise position of handset f Broken parts Please contact our spares department on 0844 372 7750 Fitting instructions are provided with spares PROFESSIONAL SERVICE If the previous checks...

Страница 6: ...ons to get the most convenient arrangement taking the following into account a The possible need to use the handset over the sink for hair washing etc b The heater must not be mounted in the direct sp...

Страница 7: ...connected to the mains cold water supply This must have a minimum running pressure of 100kPa 1 0 bar 4 5 p s i and a maximum pressure of 1000kPa 10 bar 145 p s i Before connecting the pipe work to the...

Страница 8: ...ulations If in doubt consult a qualified electrician 1 The shower is designed for a single phase A C electrical supply Please check the rating plate on the unit to see what details apply 2 The table i...

Страница 9: ...and then operate the shower as explained previously and check a That the water gets to a satisfactory temperature b Power selection does give a change in water temperature c Check again for leaks d Th...

Страница 10: ...DAMAGE REPLACE IF NECESSARY OR EVERY TWO YEARS WITH OUR APPROVED PART Additional Accessories Catalogue Number White 2 metre Shower hose 83 792578 WRAS Listed Water Isolating Valve 93 792452 Shower de...

Страница 11: ...11 Diagram 13...

Страница 12: ...or ULTRA FINISHING LIMITED WIDOW HILL ROAD HEASANDFORD INDUSTRIAL ESTATE BURNLEY LANCS BB10 2BE TEL 01282 436934 FAX 01282 428915 Technical Advice Line 0844 372 7766 Website www ultra group co uk A4 L...

Отзывы: