Triple Solar assembly instruction PVT heat pump panels March 2020
Figure 5.1-c Pitched roof mounting instruction roof brackets (dimensions in mm)
•
Place the first mounting rail on the roof brackets and slide the cross connector into the groove
on the side of the mounting rail. Tighten the mounting rail by tightening the flange nut of the
cross connector to 26Nm (drive SW13). See also figure 5.1-d as an example.
•
If more than one rail is to be connected, insert the mounting rail connector into the next rail
and repeat step 4.
•
For the next row, consider the vertical distance between the rows of heat pump panels.
Distance between panels at least 40mm.
•
With some roof tiles it is necessary to slightly grind the tiles at the bottom as a recess for the
roof brackets.