46
Transport, Installation, Commissioning
TNL12.2
DTE070EN - 15.09.2021
Installing the configuration levels and additional equipment
Installing the cooling lubricant unit
• Push the cooling lubricant unit from the left side of the machine under the
machine (1.), then push it to the right until it stops (2).
Make sure that the front of the chip conveyor is flush with the base of the
machine (3).
Contact surface
2
.
1.
3.
Содержание TNL12.2
Страница 6: ...6 Transport and installation TNL12 2 DTE070EN 15 09 2021 Table of Contents ...
Страница 8: ...8 Transport TNL12 2 DTE070EN 15 09 2021 Safety ...
Страница 16: ...16 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 General ...
Страница 32: ...32 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 Transporting the machine ...
Страница 44: ...44 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 Installing the machine ...
Страница 50: ...50 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 Electrical connection ...
Страница 52: ...52 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 Pneumatic connection ...
Страница 56: ...56 Transport installation commissioning TNL12 2 DTE070EN 15 09 2021 Commissioning ...
Страница 61: ......