33
Transport, Installation, Commissioning
TNL12.2
DTE070EN - 15.09.2021
Installing the machine
Electrical connection
Check the connected load according to the data and conditions in Chapter
Elec-
trical connection
.
Aligning and doweling the machine
Spirit level and support surface
• Place the spirit level on the support surface on the counter spindle
(4)
.
The position of the counter spindle corresponds to the position with a trans-
port lock.
If necessary, move the counter spindle to the position, see
Axis positions for
attaching the transport locks
.
4
Installation items
For installation items
A
-
D
, see Chapter
Installation plan
.
The machine is aligned exclusively with the installation items
A, B
and
D
.
• Completely relieve the load on the installation item
C
.
Содержание TNL12.2
Страница 6: ...6 Transport and installation TNL12 2 DTE070EN 15 09 2021 Table of Contents ...
Страница 8: ...8 Transport TNL12 2 DTE070EN 15 09 2021 Safety ...
Страница 16: ...16 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 General ...
Страница 32: ...32 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 Transporting the machine ...
Страница 44: ...44 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 Installing the machine ...
Страница 50: ...50 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 Electrical connection ...
Страница 52: ...52 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 Pneumatic connection ...
Страница 56: ...56 Transport installation commissioning TNL12 2 DTE070EN 15 09 2021 Commissioning ...
Страница 61: ......