HOW TO SIZE REFRIGERANT LINES

 

 

In the dimensioning of refrigerant lines of air conditioning systems equipped with two sections, the designer has to take into account 

that, due to the pressure loss of the refrigerant circuits, cooling capacity decrease and compressors power input increase may occur. 

It is also necessary to consider that the fluid changes its state when circulating within the plant. 

Another common problem is related to the oil: this, in fact, is highly miscible to the refrigerant and consequently it is easily dragged 

into the circuit; obviously, it is necessary to make sure that this lubricant is able to entirely come back to the compressor. Finally, the 

following basic conditions, typical of each refrigerant circuit, must be respected: cleaning of the pipes and total absence of liquid to the 

compressor's inlet. 

To avoid all the above-mentioned problems, the connection lines must be properly sized.

 

 

7.1

 DIAMETER 

The pipes diameter is one of the most critical features in sizing the refrigerant lines. The refrigerant speed inside the pipes 

and the pressure drop depend on the diameter. 

Although it is advisable to limit as much as possible the pressure drop (to reduce the loss of cooling capacity) is important 

to ensure a velocity in the pipe to allow the oil carryover. 

Generally the dimensioning of the suction line is made in order to maintain a speed higher than 4 m/s to the minimum load 

(minimum step of capacity) and lower than 20 m/s at full load. 

The tables below show the standard diameters. These diameters shall be considered approximate and must be verified for 

each installation. 

 

 

RAUS STANDARD DIAMETERS 

SIZE 

Suction 

diameter  

[mm] 

Liquid 

diameter  

[mm] 

040 

22 

12 

050 

22 

12 

070 

22 

12 

080 

22 

12 

090 

22 

12 

100 

22 

12 

110 

22 

12 

130 

28 

16 

150 

28 

16 

 

RAUS connection kit includes solenoid valve, mechanical expansion valve, filter dryier with liquid sight and safety valve. 

 

RAUX STANDARD DIAMETERS 

SIZE 

Suction diameter  

 [mm] 

Liquid diameter  

[mm] 

Balancing 

diameter 

[mm] 

040 

22 

12 

12 

050 

22 

12 

12 

060 

22 

12 

12 

070 

22 

12 

12 

080 

22 

12 

12 

090 

22 

12 

12 

100 

22 

12 

12 

120 

28 

16 

16 

140 

28 

16 

16 

 

RAUX loose connection kit includes 2 check valves, 1 mechanical expansion valve. 

RAUX  mounted connection kit includes: 2 safety valves on liquid line, 2 shut-off valves on liquid line and 1 shut-off valve 

on suction line. 

 

 

Содержание RAUS 040

Страница 1: ... condensing units Air cooled chillers and heat pumps condensing units with scroll compressors RAUS 040 150 Cooling capacity 16 5 52 2 kW RAUX 040 140 Cooling capacity 15 2 48 2 kW Heating capacity 17 1 53 7 kW July 2021 CG SVX052A GB Original instructions ...

Страница 2: ...OW TO SIZE REFRIGERANT LINES 11 8 LIQUID RECEIVER 19 9 REMOTE TERMINALS CONTROL AND EXPANSION VALVE 22 10 ELECTRICAL PANEL 23 11 OPERATOR RESPONSABILITIES 24 12 START UP PRELIMINARY PROCEDURES 24 13 CHECK LIST MANDATORY OPERATION CONTROL BEFORE START UP 25 14 MAINTENANCE 29 15 RECOMMENDED SPARE PARTS 32 16 TROUBLESHOOTING 33 17 IMPROPER USES 35 ...

Страница 3: ...on observance of the above mentioned rules and of all the indications written on this manual will cause the immediate loss of warranty getting free TRANE from any responsibility for the unit and any damages to persons or things 1 3 RECEIVING THE UNIT On receiving the unit it is up to the customer to check that there is no obvious damage or pieces missing If this is so an immediate complaint must b...

Страница 4: ...arry out all the maintenance operations provided for by this manual regularly wear a protective helmet before entering inside the unit before opening a machine panel make sure that it is firmly connected by means of a hinge do not touch the air condensation batteries without having first put on protective gloves do not remove the protections to the moving parts while the unit is running before res...

Страница 5: ...tained in the refrigerant circuit into the environment when replacing the electronic card always use appropriate equipment extractor anti static bracelet etc if a compressor the condensation batteries or any other heavy part is to be replaced make sure that the lifting equipment matches the weight to be lifted if the unit has an independent compressor compartment do not open the ventilator compart...

Страница 6: ...ation can damage electronic components 3 2 OPERATING LIMITS Unit operation is permitted within the limits indicated in the diagram provided in 3 3 CAUTION The operation outside the limits specified may cause the activation of the protections and disrupt the operation of the unit and in extreme cases damage the unit In case of doubt consult the factory These operating limits apply to unit operating...

Страница 7: ...Page 7 RAUX 040 140 HEATING MODE RAUX 040 140 COOLING MODE OAT Outdoor Air Temperature C ET Evaporating Temperature C OAT Outdoor Air Temperature C CT Condensing Temperature C kit 10 C Glycol ...

Страница 8: ...the transmission of vibrations to the supporting structures fit shock absorbers in every fastening point Rubber shock absorbers are recommended for units installed on the ground spring shock absorbers for units installed on roofs Open spaces around the unit must be provided to allow for the passage of necessary airflow and to allow normal maintenance to be carried out IMPORTANT Make sure that duri...

Страница 9: ... units with horizontal flow fans that such winds blow in front of the unit fans discharge side In case of unit with vertical flow fans it is strictly necessary to avoid installations where the dominant winds could cause rejected hot air to come back to the condensing coils 4 4 PRECAUTIONS AGAINST DIRECT SUNSHINE Direct solar radiation can raise the temperature of condensation until it causes the u...

Страница 10: ...cable of a section which is appropriate to the machine absorption The switch and the fuses like all the power connections must comply with the regulations in force 6 2 IMBALANCE BETWEEN THE SUPPLY TENSION PHASES Do not run the electrical motors when the voltage unbalance between the phases is more than 2 Use the following formula to check Imbalance Vx Vave x 100 Vave Vave V1 V2 V3 3 Vx phase with ...

Страница 11: ...pipes and the pressure drop depend on the diameter Although it is advisable to limit as much as possible the pressure drop to reduce the loss of cooling capacity is important to ensure a velocity in the pipe to allow the oil carryover Generally the dimensioning of the suction line is made in order to maintain a speed higher than 4 m s to the minimum load minimum step of capacity and lower than 20 ...

Страница 12: ...temperature drops C on the suction and discharge lines Losses of load C Power output Power input 0 100 100 1 C suction 95 7 103 5 1 C discharge 98 4 103 5 2 C suction 92 2 106 6 2 C discharge 96 8 106 6 High pressure drops caused by considerable lengths create another type of problem on the liquid line known as gas flashing It consists in the evaporation of part of the refrigerant due to the heat ...

Страница 13: ...ngths are shown in the table 2 and shall be considered effective for fully open valves Table 2 Equivalent lengths in meters for concentrated drops The table1 is referred to a condensation temperature of 40 C In case of different condensation temperatures the following correcting values shall be applied to the cooling capacity Cond Temp C 20 30 40 50 K suction line 1 18 1 1 1 0 91 K discharge line ...

Страница 14: ... The cooling capacity delivered by the line with Δext 28 mm corresponding to pressure drops of 0 02 k m is therefore P 29 7 x1 11 32 97 kW In conclusion the data we need to use the formula 1 are the following ΔT 0 016x60 0 96 K ΔTtab 0 02 K Le 1m Leff 60m P 32 97 kW As a consequence The above value represents the cooling capacity for a line with Δext 28mm at Tas 5 C e Tc 50 C and with a correspond...

Страница 15: ... in case of different temperature values of the liquid line the capacities must be adjusted according to the following factors Liquid temperature C 30 40 50 Correction factor 1 08 0 91 0 82 Table 3 a Correction factors for different liquid temperature Table 4 Minimum capacity kW ensuring the oil flowing in vertical sections of the discharge line R410a In this case also the cooling capacity shown i...

Страница 16: ... a single line dimensioned in accordance to the maximum cooling capacity Between the two vertical sections a sump is realized The sump is sized to guarantee that at minimum loads it will be filled with oil closing the entrance to the line B The sump however must not contain excessive amounts of oil but it must have a minimum volumetric capacity When the cooling capacity grows the greater flow crea...

Страница 17: ...ed using check valves and making oil taps if the condenser is mounted at a higher level than the compressor On the liquid line it is important to avoid that non liquid refrigerant reaches the thermostatic valve This purpose is achieved by giving to the fluid a high subcooling in the condenser but a proper sized liquid receiver shall be installed upstream from the line in the case of high lengths o...

Страница 18: ...e Temperature C 20 0 25 50 75 100 125 Expansion mm mt 0 0 4 0 7 1 1 1 5 1 9 2 3 These special couplings or U shaped or L shaped sections used to compensate the pipe expansion can be sized according to the following sketch Since this type of components may cause significant pressure drops their use must be carefully evaluated Supports shall be installed to support the pipes weight and shall be spac...

Страница 19: ...k as condenser or as evaporator in accordance with the cycle The liquid receivers are installed on the refrigerant circuit and allow to store the charge difference between the two cycles The placement of the liquid receiver shall be evaluated depending on the capacity of the heat exchangers of the plant and those installed on board of the unit For example Capacity of the heat exchanger on board 10...

Страница 20: ...S SIGHT GLASS PS SERVICE VALVE KA HP TRANSDUCER KB LP TRANSDUCER F FILTER BCE EVAPAPORATING R SHUT OFF VALVE OPTION V FAN Rliq LIQUID RECEIVER PB LP PRESSURE VL SOLENOID VALVE Tair AIR TEMPERATURE PROBE PFV24 PRESSURE SWITCH FOR THE ACTIVATION DEACTIVATION OF ONE FAN STANDARD FOR SIZES 125 128 133 136 145 150 CONNECTION BY THE CUSTOMER REFRIGERANT 410a RAUS 040 150 ...

Страница 21: ...IQUID RECEIVER BCE EVAP COND COIL V2 CIRCUIT VALVE V FAN KB LP TRANSDUCER PB LP PRESSURE SWITCH VA LIQUID SAFETY VALVE OPTION Tas SUCTION TEMPERATURE PROBE AA ACCUMULATOR VIC CYCLE INVERSION VALVE TSC COMPR DISCHARGE TEMPERATURE with 15 C h t kit VEE ELECTRONIC EXPANSION VALVE KD ELECTRONIC EXPANSION VALVE REFRIGERANT 410a Liquid receiver in chiller mode Liquid receiver in heat pump mode CONNECTIO...

Страница 22: ...receiver shall be placed in a location that ensure the proper filling during the operation in chiller mode and the proper emptiness during heat pump mode IMPORTANT The choice of the liquid receiver capacity and its placing is the responsibility of the designer of the plant 9 REMOTE TERMINALS CONTROL AND EXPANSION VALVE The units can be connected to hydronics or direct expansion terminals In both c...

Страница 23: ...auxiliary transformer control circuit 230 24V It requires no additional power cable for the control equipment The circuit also an electric resistance installed in the compressor in order to keep warm the oil and thus avoid the transmigration of the refrigerant in its interior Obviously the operation of the electrical resistors is ensured as long as the unit is power supplied The unit is equipped w...

Страница 24: ... CHECK With the general switch open check that the electrical connections are tightly clamped Check for any possible refrigerant leaks Check that the electrical data on the label correspond to those of the mains supply Check that the thermal charge available is appropriate for starting 12 2 REFRIGERANT SEALS CONTROL Units are shipped void of refrigerant pressed with nitrogen and with pipes plugged...

Страница 25: ...T OR THE HYDRAULIC CIRCUIT OR THE ELECTRICAL PANEL OR CHANGES TO THE UNIT OPERATING PARAMETERS MADE BY A THIRD PERSON WITHOUT A WRITTEN AUTHORIZATION ISSUED BY TRANE THE UNIT SHALL BE CONFORM TO TRANE WIRING DIAGRAMS AND TECHNICAL DOCUMENTATION IN CASE OF RELEVANT DIFFERENCE BETWEEN THE UNIT AND TRANE STANDARD CONFIGURATION PLEASE CONTACT TRANE WARNING PLEASE BE AWARE THAT RELEVANT DAMAGES CAUSED ...

Страница 26: ... BEFORE THE START UP 16 AN ELECTRONIC SUPERVISOR OR ANY ADDITIONAL CONTROLLER HAS BEEN INSTALLED 17 THE CONNECTION WIRES ARE SHIELDED 18 REMOTE CONTROL DEVICES OR INTERFACES ARE CONNECTED TO THE ELECTRICAL PANEL IN CONFORMITY WITH TRANE WIRING DIAGRAMS 19 ELECTRONIC DEVICES ARE INTACT AND DON T DISPLAY ANY DAMAGE 20 THE ELECTRICAL ABSORPTION IS STANDARD REFRIGERANT CIRCUIT COMPLIANCE YES NO 21 ALL...

Страница 27: ...lues may mean an excess of charge After intervention on the charge it is appropriate to check that the unit runs within the declared values with unit steadily running on a full charge measure the temperature of the suction line downstream of the thermostatic valve bulb read the balance pressure to the evaporator on the low pressure manometer and the corresponding saturation temperature Overheating...

Страница 28: ...nsumption and possible damage to the compressor The symptoms of a low refrigerant charge are Low evaporation pressure High value of superheating Low value of subcooling In this case add refrigerant R410A The system is provided with a charging port between the expansion valve and the evaporator Charge refrigerant until conditions return to work normal Remember to replace the cap closing the valve a...

Страница 29: ...ns of the compressor It is recommended to check the value of the vibration immediately after starting and periodically on an annual basis Compressor Electrical Connections It is very important that all the compressors are wired correctly for proper rotation These compressors will not tolerate reverse rotation Verify correct rotation phasing using a rotation meter If wired incorrectly the compresso...

Страница 30: ...ing with cleansers or detergents is strongly discouraged due to the all aluminum construction straight water should prove sufficient if not please contact TRANE Any breach in the tubes can result in refrigerant leaks IMPORTANT Only in extreme cases should any type of chemical cleaner or detergent be used on microchannel coils If it becomes absolutely necessary because water alone did not clean the...

Страница 31: ...eck through the sight glass coolant flow Full Indicator X Check the pressure drop of the filter drier X Carry out the analysis of the vibrations of the compressor X Carry out the analysis of the acidity of the oil of the compressor 5 X Condensing section Cleaning the condenser coils 4 X Check that the fans are tightened X Notes 1 The monthly activities include all those weekly 2 The annual activit...

Страница 32: ...ght glass 1 per type fans and engines 1 per type 2 YEAR COMPONENTS QUANTITY fuses all filter dryers all solenoid valves all electronic expansion valves all pressure switches all gas gauges all contactors and relays all thermal protectors all carter electric heaters all 4 way valve 1 per type check valve 1 per type sight glass 1 per type fans and engines 1 per type electrical components all compres...

Страница 33: ...e in the circuit Make sure that working conditions are within the limits of operation Loss of coolant see section G C The compressor starts up and stops repeatedly x x s Intervention of the minimum See point E x x s Compressor contactor defective Check and replace if necessary x x u Calibration values of the set point or differential Modify them as reported in the in the tables x x s Lack of coola...

Страница 34: ...and the continuity of the coil x x s Lack of output voltage from the control fan speed Check the contacts replace if necessary x x s Thermal protection inside the fan Check the condition of the fan and the air temperature during operation of the unit x x s Fan motor faulty Check and replace x x s Loose electrical connections Check and replace G Lack of gas x x s Loss in the refrigerant circuit Che...

Страница 35: ...The panel vibrate Fasten properly O The defrosting cycle is never activated x s 4 way reversing valve defective Check the power supply and the coil of the valve and replace the valve x s The defrost thermostat is worn out or has an incorrect calibration value Check and replace if defective or change the calibration value P The unit does not start x x s Phases of the supply network reversed Invert ...

Страница 36: ...portfolio of heating ventilating and air conditioning systems and controls services parts and supply For more information please visit trane eu or tranetechnologies com Trane has a policy of continuous product and product data improvement and reserves the right to change design and specifications without notice 2021 Trane CG SVX052A GB_0721 New ...

Отзывы: