![Trane Climate Changer T Series Скачать руководство пользователя страница 43](http://html.mh-extra.com/html/trane/climate-changer-t-series/climate-changer-t-series_installation-operation-and-maintenance_1149559043.webp)
CLCH-SVX06A-EN •
T-Series Climate Changer Air Handler IOM
43
Installation-Mechanical
1.
Verify that the shipping bolts that hold the fan base in a fixed position have been
removed.
2. Remove the jam nut on top of the isolator adjusting stud at the first isolator to be
adjusted. Check that the shipping block is in place.
3. Turn the adjusting nut 2 or 3 turns only, counterclockwise on each isolator in a
sequenced manner. The equipment weight will compress the spring inside the
housing approximately 1/4 inch.
4. Check that the bushing on the isolator stud is centered in the isolator. Adjust to center
by moving the stud in the fan base hole.
Note: This procedure will raise the equipment load until the isolators are all off the shims
(shipping tie-down blocks) approximately 1/32-inch (the thickness of a credit card),
and the internal gap is approximately equal to the external gap. Do not adjust
isolators once the fan base is off of the shipping tie down blocks.
5. Continue adjusting other isolators in sequence and repeat the same adjustment.
Continue until all isolators are adjusted.
6. Replace the jam nut on each isolator adjusting bolt, tighten the nut, and remove the
shipping tie down block.
Table 8. Isolator minimum clearance adjustments (in)
Unit size
Fan type
Isolator type
Required clearance
3-8
FC and AF
Spring
1.0
10-30
FC and AF
Spring
0.5
21-57
Plenum
Spring
0.5
35-57
FC and AF
Spring
0.5
66-100
FC, AF and Plenum
Spring
1.0